PLAN REV 1.2MILESTONES 14COMPONENTS 26UPDATED 2026-11-17LICENSE CC BY-SA 4.0
Every piece of hardware the plan relies on

Technology register

Each technology, which milestone uses it, how ready it is (TRL), and its source. Items marked "develop" need further work within the 3–5 year rule.
TechnologyMilestoneUsed forStatusTRL
Lunar Reconnaissance Orbiter (LRO)M00Terrain, imagery, temperature and radar data for site selectionOperating; FY2026 budget request continues operations to support CLPS deliveries, landing-site characterisation and Artemis 9
ShadowCam on KPLO/DanuriM00Images inside permanently shadowed cratersOperating in extended mission; expected to end in early 2028 when its battery runs out in a lunar eclipse 9
Chandrayaan-2 orbiter DFSAR radarM00Radar evidence of subsurface iceDFSAR data showed possible subsurface ice under four doubly shadowed craters (ISRO, May 2026) 9
NASA Artemis south-pole candidate regionsM00Starting shortlist of pre-screened regions9 regions published Oct 2024 (for Artemis III) 9
TRIDENT drill (Honeybee Robotics)M01Drilling up to 1 m to sample iceFlew on IM-2 (2025). Powered up and extended to its full range; lander ended on its side and the mission ended early 7
MSolo mass spectrometerM01Identifying volatiles released from drilled soilFlew on IM-2; worked, but gases detected were from the lander or Earth 7
VIPER rover (NASA)M01Partner ice-prospecting dataRevived Sep 2025 via CLPS task order up to $190M; delivery option tied to Blue Moon MK1's first flight 8
Commercial lunar landers (CLPS)M01Delivering the prospectorMixed record: Peregrine never attempted a landing (2024); IM-1 and IM-2 tipped; Blue Ghost M1 fully successful (2025) 7
Radioisotope heater unitsM01Keeping electronics warm in PSRs and at nightFlight-proven (Cassini carried 82), about 1 W each 9
Firefly Blue Ghost landerM02Small cargoFully successful landing Mar 2025; 14 days of operations 9
Intuitive Machines Nova-CM02Small cargoLanded twice (2024, 2025); both times ended on its side 7
Astrobotic GriffinM02Small cargoFirst flight planned January 2027 6
Blue Origin Blue Moon Mark 1M02Medium cargo (up to 3 t)Pathfinder to Shackleton connecting ridge NET Q1 2027 6
SpaceX Starship HLS / cargoM02Heavy cargo and crewStarship reached orbit on flights 14 and 15 (2026); ship caught by the tower after flight 15 6
Blue Origin Blue Moon Mk2M02Crew; cargo variant~$3.1B NASA contract; uncrewed demo expected Feb 2029 5
Lunar Surface Manipulation System (LSMS)M02Offloading craneGround prototypes tested; NASA proposed path to TRL 6 4 develop
NASA commercial lunar relay (Intuitive Machines)M03Earth link and PNTContract with a maximum potential value of $4.82B (Sep 2024) 7
ESA MoonlightM03Earth link and navigation5 satellites; initial operations by end 2028, full operations by 2030 6
SSTL Lunar PathfinderM03RelayIn final testing; launch NET 2027 on Blue Ghost M2 7
Nokia lunar 4G/LTE networkM03Surface networkRan for its full ~25-minute power window on IM-2 (2025) 7
LuGRE GPS/Galileo receiverM03NavigationGot a position fix on the lunar surface, Mar 2025 7
Optical (laser) communicationsM03High-rate Earth linkLCRD experimenting since 2022; O2O flew on Artemis II (2026) at up to 260 Mbps 7
LunaNet Interoperability Specification v5M03Standard so all networks work togetherVersion 5 published Feb 2025; developed by NASA, ESA, JAXA 9
Kilopower / KRUSTY fission testM04Heritage for the reactor28-hour nuclear system test 2018 at various power levels; Stirling converters worked 5
US Lunar Reactor-1 (SPARC)M04Reactor procurement pathDraft solicitation Aug 2026: ≥20 kWe, ≥5 yr, HALEU, closed Brayton, <15 t. No award yet 5
Vertical Solar Array Technology (VSAT)M0410 kW-class solar towersThree NASA prototype contracts (2022); deploy to ~10 m 6
Astrobotic VSAT-XLM0450 kW towersNASA SBIR study award 2024; 34 m tall; Redwire ROSA arrays. Phase II follow-on Jun 2025–Jun 2027 5 develop
Astrobotic LunaGrid-LiteM04Cable-laying rover and power transfer1 kW; ~500 m of cable in the 2025 design (1 km in earlier plans); passed CDR Aug 2025 6
Regenerative fuel cellsM04Night and gap storageNASA Glenn breadboard ran 550+ hours of simulated lunar cycles (open-loop) 5 develop
High-voltage DC lunar cableM04Power transmissionNASA Glenn analysis: ±4 kVDC Al cable best for 3 km at 95% 5
NASA ISRU Pilot Excavator (IPEx)M05Excavation and gradingTRL 5 design (2024); target 42 kg/h, 10 t over an 11-day mission; no flight date 5
RASSOR 2.0M05Light excavationUnder 100 kg; nominal mission concept of 35 loads of 20 kg per 24 h, about 700 kg/day 5
ICON Project Olympus (laser vitreous transformation)M05Pads, roads and structures from regolith$57.2M NASA SBIR Phase III contract (2022) for landing pads, blast shields and roads 4 develop
Sintered basalt pavers / regolith-polymer padsM05Landing padsHot-fire tested on the ground by NASA KSC 4 develop
Molten regolith electrolysis (NASA + Lunar Resources)M06Oxygen from rock2024: 25 kg of simulant processed in vacuum, 0.07 kg O₂/h for 9 h 4 develop
Carbothermal reduction (Sierra Space + NASA)M06Oxygen from rock (alternative)Flight-like reactor ran automated in JSC dirty thermal-vacuum chamber (2024); key hardware matured to TRL 6 6
Blue Origin Blue AlchemistM06Oxygen plus silicon, iron, aluminiumPassed CDR Sep 2025; autonomous demo in simulated lunar environment planned 2026 5 develop
Molten salt electrolysis (Metalysis process, ESA)M06Oxygen with metal by-productESA prototype plant opened 2020; extracts oxygen and leaves a mix of metals 4 develop
ISS Oxygen Generation AssemblyM06Water electrolysisFlight-proven since 2007; nominal 5.4 kg O₂/day 9
Ice excavation (NASA Break the Ice)M06Mining icy regolithChallenge winners 2024; designs ground-tested 4 develop
Astrolab CLV-1 (LTV)M07Crew and cargo roverNASA task order $219M (May 2026); flight units to be qualified over the next 18 months; delivery 2028 6
Lunar Outpost Pegasus (LTV)M07Crew and cargo roverNASA task order $220M (May 2026); delivery 2028 6
JAXA/Toyota pressurised rover (Lunar Cruiser)M07Long crewed trips2024 agreement: 2 crew up to 30 days, ~10-year life; NASA lists 28 days; cargo delivery NET FY2032 5
Delay-tolerant teleoperationM07Earth-driven roversNASA LTV studies: operators completed traverses at 4, 6 and 8 s delay (2023) 6
NASA CADRE autonomous roversM07Multi-robot autonomy heritageFlies on Intuitive Machines IM-3; NASA launch schedule lists IM-3 for early 2027 6
Thales Alenia Space Multi-Purpose Habitation (MPH)M08Surface habitatPreliminary design contract with ASI (Jul 2025); ~15 t, ~3 m × 6 m, 10-yr life; launch planned 2033 5
Sierra Space LIFE inflatableM08Alternative expandable habitatFull-scale burst test reached 77 psi before bursting (reported Jan 2024), 27% above NASA's recommended 60.8 psi 5
ISS life support (ECLSS)M08Air and water recyclingFlight-proven; 98% water recovery demonstrated 2023 9
Axiom AxEMU spacesuitM08MoonwalksCritical design review closed 13 Nov 2026; qualification next 6
Heavy cargo lander (Starship / Blue Moon Mk2 cargo)M08Habitat delivery~15 t class; habitat delivery NET FY2033 per NASA 6
ISS water recovery with Brine ProcessorM09Water recycling98% recovery demonstrated (2023) 9
ISS Oxygen Generation AssemblyM09Oxygen from waterFlight-proven; ~5.4 kg O₂/day for 4 crew 9
Four-bed CO₂ scrubber (4BCO2)M09CO₂ removalISS flight demonstration for 4 crew-equivalents 7
Sabatier reactorM09Water from CO₂Flown on ISS; limits O₂ recovery to ~50% because methane is vented 8
Regolith radiation shieldingM09Protect crew in habitatsNo single NASA design value; models suggest ≥2 m 4 develop
NASA VeggieM10Leafy greensISS plant facilities (Veggie and APH) have grown lettuces, Chinese cabbage, mustard greens, kale 9
NASA Advanced Plant HabitatM10Controlled growth of fruiting cropsChile peppers bore fruit on ISS; harvests planned late Oct and early Nov 2021 9
Yuegong-1 (Lunar Palace 1) bioregenerative systemM10Closed-loop life support with crops370 days, 8 crew in two groups of four (2017–18); 98.2% material closure on the ground 6
ESA MELiSSAM10Closed-loop ecosystem researchPilot plant at Universitat Autònoma de Barcelona since 2009 4 develop
Interstellar Lab NUCLEUSM10Compact food productionWon NASA Deep Space Food Challenge grand prize 2024 5
Pilot plant results (M06)M11Basis for scale-upTo be demonstrated 5
Cryogenic propellant transferM11Refuelling landersStarship propellant transfer demo shown ~Q1 2027 on NASA HLS schedule 5 develop
In-orbit LOX storage demo (LOXSAT)M11Cryogenic storage heritageEta Space payload on Rocket Lab spacecraft; NASA (May 2026) gave launch no earlier than 17 July 6
Blue Origin Blue AlchemistM12Silicon, solar cells, wire from regolithCompany reports solar cells and wire from simulant; passed CDR 2025; autonomous ground demo planned 2026 5 develop
ESA metal 3D printer on ISSM12Printing metal partsFirst metal part printed in space, Aug 2024 7
Redwire / Made In Space AMF on ISSM12Polymer partsCommercial polymer printer on ISS (ABS, ULTEM, HDPE); parts printed since at least Feb 2017 9
Redwire Regolith PrintM12Printing with regolith simulantPrinted with regolith simulant on ISS (launched Aug 2021) 5
ICON Project OlympusM12Regolith construction$57.2M NASA SBIR Phase III contract 4 develop
Molten salt electrolysis (Metalysis/ESA)M12Metals + oxygenESA prototype plant (2020); leaves a tangle of mixed metals 4 develop
Everything in M00–M12M13FoundationSee earlier milestones 4
Lava tubesM13Future shielded volumeRadar evidence of a cave under the Mare Tranquillitatis pit (2024); Marius Hills pit ~40 m deep 2 develop
ProjectOPEN MOON · Self-sustaining lunar colony
DocumentOM-300
Revision1.2 · Draft