Every piece of hardware the plan relies on
Technology register
Each technology, which milestone uses it, how ready it is (TRL), and its source. Items marked "develop" need further work within the 3–5 year rule.
| Technology | Milestone | Used for | Status | TRL |
|---|---|---|---|---|
| Lunar Reconnaissance Orbiter (LRO) | M00 | Terrain, imagery, temperature and radar data for site selection | Operating; FY2026 budget request continues operations to support CLPS deliveries, landing-site characterisation and Artemis | 9 |
| ShadowCam on KPLO/Danuri | M00 | Images inside permanently shadowed craters | Operating in extended mission; expected to end in early 2028 when its battery runs out in a lunar eclipse | 9 |
| Chandrayaan-2 orbiter DFSAR radar | M00 | Radar evidence of subsurface ice | DFSAR data showed possible subsurface ice under four doubly shadowed craters (ISRO, May 2026) | 9 |
| NASA Artemis south-pole candidate regions | M00 | Starting shortlist of pre-screened regions | 9 regions published Oct 2024 (for Artemis III) | 9 |
| TRIDENT drill (Honeybee Robotics) | M01 | Drilling up to 1 m to sample ice | Flew on IM-2 (2025). Powered up and extended to its full range; lander ended on its side and the mission ended early | 7 |
| MSolo mass spectrometer | M01 | Identifying volatiles released from drilled soil | Flew on IM-2; worked, but gases detected were from the lander or Earth | 7 |
| VIPER rover (NASA) | M01 | Partner ice-prospecting data | Revived Sep 2025 via CLPS task order up to $190M; delivery option tied to Blue Moon MK1's first flight | 8 |
| Commercial lunar landers (CLPS) | M01 | Delivering the prospector | Mixed record: Peregrine never attempted a landing (2024); IM-1 and IM-2 tipped; Blue Ghost M1 fully successful (2025) | 7 |
| Radioisotope heater units | M01 | Keeping electronics warm in PSRs and at night | Flight-proven (Cassini carried 82), about 1 W each | 9 |
| Firefly Blue Ghost lander | M02 | Small cargo | Fully successful landing Mar 2025; 14 days of operations | 9 |
| Intuitive Machines Nova-C | M02 | Small cargo | Landed twice (2024, 2025); both times ended on its side | 7 |
| Astrobotic Griffin | M02 | Small cargo | First flight planned January 2027 | 6 |
| Blue Origin Blue Moon Mark 1 | M02 | Medium cargo (up to 3 t) | Pathfinder to Shackleton connecting ridge NET Q1 2027 | 6 |
| SpaceX Starship HLS / cargo | M02 | Heavy cargo and crew | Starship reached orbit on flights 14 and 15 (2026); ship caught by the tower after flight 15 | 6 |
| Blue Origin Blue Moon Mk2 | M02 | Crew; cargo variant | ~$3.1B NASA contract; uncrewed demo expected Feb 2029 | 5 |
| Lunar Surface Manipulation System (LSMS) | M02 | Offloading crane | Ground prototypes tested; NASA proposed path to TRL 6 | 4 develop |
| NASA commercial lunar relay (Intuitive Machines) | M03 | Earth link and PNT | Contract with a maximum potential value of $4.82B (Sep 2024) | 7 |
| ESA Moonlight | M03 | Earth link and navigation | 5 satellites; initial operations by end 2028, full operations by 2030 | 6 |
| SSTL Lunar Pathfinder | M03 | Relay | In final testing; launch NET 2027 on Blue Ghost M2 | 7 |
| Nokia lunar 4G/LTE network | M03 | Surface network | Ran for its full ~25-minute power window on IM-2 (2025) | 7 |
| LuGRE GPS/Galileo receiver | M03 | Navigation | Got a position fix on the lunar surface, Mar 2025 | 7 |
| Optical (laser) communications | M03 | High-rate Earth link | LCRD experimenting since 2022; O2O flew on Artemis II (2026) at up to 260 Mbps | 7 |
| LunaNet Interoperability Specification v5 | M03 | Standard so all networks work together | Version 5 published Feb 2025; developed by NASA, ESA, JAXA | 9 |
| Kilopower / KRUSTY fission test | M04 | Heritage for the reactor | 28-hour nuclear system test 2018 at various power levels; Stirling converters worked | 5 |
| US Lunar Reactor-1 (SPARC) | M04 | Reactor procurement path | Draft solicitation Aug 2026: ≥20 kWe, ≥5 yr, HALEU, closed Brayton, <15 t. No award yet | 5 |
| Vertical Solar Array Technology (VSAT) | M04 | 10 kW-class solar towers | Three NASA prototype contracts (2022); deploy to ~10 m | 6 |
| Astrobotic VSAT-XL | M04 | 50 kW towers | NASA SBIR study award 2024; 34 m tall; Redwire ROSA arrays. Phase II follow-on Jun 2025–Jun 2027 | 5 develop |
| Astrobotic LunaGrid-Lite | M04 | Cable-laying rover and power transfer | 1 kW; ~500 m of cable in the 2025 design (1 km in earlier plans); passed CDR Aug 2025 | 6 |
| Regenerative fuel cells | M04 | Night and gap storage | NASA Glenn breadboard ran 550+ hours of simulated lunar cycles (open-loop) | 5 develop |
| High-voltage DC lunar cable | M04 | Power transmission | NASA Glenn analysis: ±4 kVDC Al cable best for 3 km at 95% | 5 |
| NASA ISRU Pilot Excavator (IPEx) | M05 | Excavation and grading | TRL 5 design (2024); target 42 kg/h, 10 t over an 11-day mission; no flight date | 5 |
| RASSOR 2.0 | M05 | Light excavation | Under 100 kg; nominal mission concept of 35 loads of 20 kg per 24 h, about 700 kg/day | 5 |
| ICON Project Olympus (laser vitreous transformation) | M05 | Pads, roads and structures from regolith | $57.2M NASA SBIR Phase III contract (2022) for landing pads, blast shields and roads | 4 develop |
| Sintered basalt pavers / regolith-polymer pads | M05 | Landing pads | Hot-fire tested on the ground by NASA KSC | 4 develop |
| Molten regolith electrolysis (NASA + Lunar Resources) | M06 | Oxygen from rock | 2024: 25 kg of simulant processed in vacuum, 0.07 kg O₂/h for 9 h | 4 develop |
| Carbothermal reduction (Sierra Space + NASA) | M06 | Oxygen from rock (alternative) | Flight-like reactor ran automated in JSC dirty thermal-vacuum chamber (2024); key hardware matured to TRL 6 | 6 |
| Blue Origin Blue Alchemist | M06 | Oxygen plus silicon, iron, aluminium | Passed CDR Sep 2025; autonomous demo in simulated lunar environment planned 2026 | 5 develop |
| Molten salt electrolysis (Metalysis process, ESA) | M06 | Oxygen with metal by-product | ESA prototype plant opened 2020; extracts oxygen and leaves a mix of metals | 4 develop |
| ISS Oxygen Generation Assembly | M06 | Water electrolysis | Flight-proven since 2007; nominal 5.4 kg O₂/day | 9 |
| Ice excavation (NASA Break the Ice) | M06 | Mining icy regolith | Challenge winners 2024; designs ground-tested | 4 develop |
| Astrolab CLV-1 (LTV) | M07 | Crew and cargo rover | NASA task order $219M (May 2026); flight units to be qualified over the next 18 months; delivery 2028 | 6 |
| Lunar Outpost Pegasus (LTV) | M07 | Crew and cargo rover | NASA task order $220M (May 2026); delivery 2028 | 6 |
| JAXA/Toyota pressurised rover (Lunar Cruiser) | M07 | Long crewed trips | 2024 agreement: 2 crew up to 30 days, ~10-year life; NASA lists 28 days; cargo delivery NET FY2032 | 5 |
| Delay-tolerant teleoperation | M07 | Earth-driven rovers | NASA LTV studies: operators completed traverses at 4, 6 and 8 s delay (2023) | 6 |
| NASA CADRE autonomous rovers | M07 | Multi-robot autonomy heritage | Flies on Intuitive Machines IM-3; NASA launch schedule lists IM-3 for early 2027 | 6 |
| Thales Alenia Space Multi-Purpose Habitation (MPH) | M08 | Surface habitat | Preliminary design contract with ASI (Jul 2025); ~15 t, ~3 m × 6 m, 10-yr life; launch planned 2033 | 5 |
| Sierra Space LIFE inflatable | M08 | Alternative expandable habitat | Full-scale burst test reached 77 psi before bursting (reported Jan 2024), 27% above NASA's recommended 60.8 psi | 5 |
| ISS life support (ECLSS) | M08 | Air and water recycling | Flight-proven; 98% water recovery demonstrated 2023 | 9 |
| Axiom AxEMU spacesuit | M08 | Moonwalks | Critical design review closed 13 Nov 2026; qualification next | 6 |
| Heavy cargo lander (Starship / Blue Moon Mk2 cargo) | M08 | Habitat delivery | ~15 t class; habitat delivery NET FY2033 per NASA | 6 |
| ISS water recovery with Brine Processor | M09 | Water recycling | 98% recovery demonstrated (2023) | 9 |
| ISS Oxygen Generation Assembly | M09 | Oxygen from water | Flight-proven; ~5.4 kg O₂/day for 4 crew | 9 |
| Four-bed CO₂ scrubber (4BCO2) | M09 | CO₂ removal | ISS flight demonstration for 4 crew-equivalents | 7 |
| Sabatier reactor | M09 | Water from CO₂ | Flown on ISS; limits O₂ recovery to ~50% because methane is vented | 8 |
| Regolith radiation shielding | M09 | Protect crew in habitats | No single NASA design value; models suggest ≥2 m | 4 develop |
| NASA Veggie | M10 | Leafy greens | ISS plant facilities (Veggie and APH) have grown lettuces, Chinese cabbage, mustard greens, kale | 9 |
| NASA Advanced Plant Habitat | M10 | Controlled growth of fruiting crops | Chile peppers bore fruit on ISS; harvests planned late Oct and early Nov 2021 | 9 |
| Yuegong-1 (Lunar Palace 1) bioregenerative system | M10 | Closed-loop life support with crops | 370 days, 8 crew in two groups of four (2017–18); 98.2% material closure on the ground | 6 |
| ESA MELiSSA | M10 | Closed-loop ecosystem research | Pilot plant at Universitat Autònoma de Barcelona since 2009 | 4 develop |
| Interstellar Lab NUCLEUS | M10 | Compact food production | Won NASA Deep Space Food Challenge grand prize 2024 | 5 |
| Pilot plant results (M06) | M11 | Basis for scale-up | To be demonstrated | 5 |
| Cryogenic propellant transfer | M11 | Refuelling landers | Starship propellant transfer demo shown ~Q1 2027 on NASA HLS schedule | 5 develop |
| In-orbit LOX storage demo (LOXSAT) | M11 | Cryogenic storage heritage | Eta Space payload on Rocket Lab spacecraft; NASA (May 2026) gave launch no earlier than 17 July | 6 |
| Blue Origin Blue Alchemist | M12 | Silicon, solar cells, wire from regolith | Company reports solar cells and wire from simulant; passed CDR 2025; autonomous ground demo planned 2026 | 5 develop |
| ESA metal 3D printer on ISS | M12 | Printing metal parts | First metal part printed in space, Aug 2024 | 7 |
| Redwire / Made In Space AMF on ISS | M12 | Polymer parts | Commercial polymer printer on ISS (ABS, ULTEM, HDPE); parts printed since at least Feb 2017 | 9 |
| Redwire Regolith Print | M12 | Printing with regolith simulant | Printed with regolith simulant on ISS (launched Aug 2021) | 5 |
| ICON Project Olympus | M12 | Regolith construction | $57.2M NASA SBIR Phase III contract | 4 develop |
| Molten salt electrolysis (Metalysis/ESA) | M12 | Metals + oxygen | ESA prototype plant (2020); leaves a tangle of mixed metals | 4 develop |
| Everything in M00–M12 | M13 | Foundation | See earlier milestones | 4 |
| Lava tubes | M13 | Future shielded volume | Radar evidence of a cave under the Mare Tranquillitatis pit (2024); Marius Hills pit ~40 m deep | 2 develop |