Plan / Phase 2 / M07
M07 · Phase 2 · 2028–2033
Surface mobility
Get unpressurised rovers, a pressurised rover and utility robots working on the surface, so crews and cargo can move between every site.
Objective
Have at least two unpressurised crew rovers that can also drive themselves, one pressurised rover for multi-week trips, and a fleet of utility robots for hauling and inspection, all driven remotely from Earth between crew visits.
Exit criteria · what "done" means
| # | Criterion |
|---|---|
| EC-1 | Two LTVs operating at the base, each having driven at least 100 km, including driverless traverses commanded from Earth. |
| EC-2 | Pressurised rover completes a crewed 14-day trip with resupply. |
| EC-3 | Utility robots haul cargo from pads to sites without crew help. |
Workstreams · 4
1
Unpressurised rovers (LTV)
Lease rovers that carry suited crew and drive themselves when no one is there.
- Astrolab CLV-1 (~2,000 lb, >6 mph)
- Lunar Outpost Pegasus (up to 1 year, >9 mph)
- Delivery by Blue Origin in 2028
2
Pressurised rover
A mobile habitat for long trips.
- JAXA/Toyota Lunar Cruiser class
- 2 crew, ~28–30-day trips
- Suitports or airlock
3
Utility robots
Do the hauling so crews don't have to.
- Payload carts towed by LTVs
- Small inspection rovers
- Cable inspection along M04 routes
4
Teleoperation
Drive rovers from Earth between crew visits.
- Delay-tolerant driving at 6–8 s
- Autonomous hazard avoidance
- Driver training on simulators
Technology · what we use and how ready it is
| Technology | Used for | Status today | TRL |
|---|---|---|---|
| Astrolab CLV-1 (LTV)1 | Crew and cargo rover | NASA task order $219M (May 2026); flight units to be qualified over the next 18 months; delivery 2028 | 6 |
| Lunar Outpost Pegasus (LTV)1 | Crew and cargo rover | NASA task order $220M (May 2026); delivery 2028 | 6 |
| JAXA/Toyota pressurised rover (Lunar Cruiser)3 | Long crewed trips | 2024 agreement: 2 crew up to 30 days, ~10-year life; NASA lists 28 days; cargo delivery NET FY2032 | 5 |
| Delay-tolerant teleoperation5 | Earth-driven rovers | NASA LTV studies: operators completed traverses at 4, 6 and 8 s delay (2023) | 6 |
| NASA CADRE autonomous rovers9 | Multi-robot autonomy heritage | Flies on Intuitive Machines IM-3; NASA launch schedule lists IM-3 for early 2027 | 6 |
Components · detailed breakdowns
Plan of action
What’s real
- LTVs. In May 2026 NASA picked two lunar terrain vehicles:
- Astrolab CLV-1, $219M
- Lunar Outpost Pegasus, $220M
- Blue Origin gets $188M, with a $280.4M option, to deliver them to the south pole region. NASA aims to have them there by 20281.
- Pressurised rover. The JAXA/Toyota rover is planned to carry 2 crew for up to 30 days3. NASA’s 2026 page says 28 days, deployed in Phase 2 (2029–2032)4, and the cargo delivery is listed as no earlier than FY20327.
- Remote driving. NASA tests had operators drive LTVs with 4-, 6- and 8-second delays, and every operator completed the traverses5.
How Open Moon uses them
Open Moon doesn’t develop its own crew rovers. It leases LTV services and joins the pressurised-rover programme as a partner. Its own spending goes on:
- utility carts and small robots for hauling, inspection and cable patrol
- the teleoperation centre on Earth
Between crew visits, rovers are driven from Earth to keep them productive.
Step-by-step
- Agree LTV service terms for Open Moon use at the base site.
- Build a teleoperation centre and train drivers on delay simulators.
- When the LTVs land in 2028: commission them, map the roads, and start hauling for M05 and M06.
- Deliver the utility carts and robots on small landers.
- Pressurised rover: join as a partner; prepare its charging station and a dock at the habitat.
Cost build-up
| Item | Low | High | Basis |
|---|---|---|---|
| LTV services (2 rovers) | $0.45B | $1.0B | NASA's 2026 LTV task orders: $219M (Astrolab) + $220M (Lunar Outpost) [src 1]; high side adds services growth |
| Pressurised rover: partnership share | $0.5B | $1.5B | ESTIMATE; cost share in a JAXA-led programme |
| Utility robots, carts and spares, including delivery (~250 kg) | $0.2B | $0.6B | ESTIMATE; 250 kg × $0.6–1.2M/kg delivery plus hardware |
| Teleoperation centre and driver training | $0.05B | $0.2B | ESTIMATE |
| Total | $1.2B | $3.3B | ESTIMATE rover services leased or shared through partners |
Mission profile
| Window | 2028–2033 |
| Phase | 2 |
| Depends on | M02, M03, M05 |
| Unpressurised | 2 × LTV-class (Astrolab CLV-1, Lunar Outpost Pegasus) |
| Pressurised | 1 × 2-crew rover, ~28–30-day trips (JAXA/Toyota class) |
| Utility | Carts and small robots for hauling and inspection |
| Teleoperation | Earth-driven with 6–8 s delay tolerance |
| Cost | $1.2–3.3B EST. |
Lowest critical TRL · 6 / 9
Failure modes · 4
FM-1 · High
Rovers are scheduled to arrive on a lander (Blue Moon Mk1) that hasn't flown yetFix: Keep a second delivery option; don't schedule crew sorties until at least one LTV is on the surface
FM-2 · High
The pressurised rover's date is unclear (Artemis VII tie, NET FY2032 delivery)Fix: Plan Phase 2 sorties to work without it, within walking/LTV range of the habitat
FM-3 · Medium
Dust wear on wheels, seals and joints over long distancesFix: Sintered roads (M05); scheduled maintenance; dust-tolerant designs
FM-4 · Medium
Driving in long shadows and low sun angles at the poleFix: Lidar and headlights; mapped roads with beacons
Sources
- NASA RELEASE26-046: NASA provides update on Moon Base rovers, landers, missions (May 2026)
- NASA: NASA selects companies to advance Moon mobility for Artemis missions (LTV $4.6B IDIQ) (Apr 2024)
- NASA: NASA, Japan advance space cooperation, sign agreement for lunar rover (Apr 2024)
- NASA Moon Base – Phases (2026)
- NASA NTRS 20240001217: LTV remote driving with time delay (2024)
- JPL: CADRE ()
- NASA HLS IAC 2026 presentation (pressurised rover cargo delivery NET FY2032) (Oct 2026)
- Toyota: Lunar Cruiser (2026)
- NASA launch schedule (Moon Base: Intuitive Machines IM-3, early 2027) (Nov 2026)