Plan / Phase 1 / M06
M06 · Phase 1 · 2029–2033
Oxygen and water pilot plants
Make the first oxygen from rock and the first water from polar ice at pilot scale, proving the processes that every later milestone depends on.
Objective
Operate an oxygen-from-regolith pilot plant and a water-from-ice pilot plant on the surface, each making at least 10 t per year, and store the products, before the first crew depends on them.
Exit criteria · what "done" means
| # | Criterion |
|---|---|
| EC-1 | Oxygen plant runs autonomously for at least 6 months and produces at least 10 t of O₂ per year at a rate that scales with added modules. |
| EC-2 | Water plant extracts water from PSR regolith and delivers purified water to storage at a rate of at least 10 t per year. |
| EC-3 | Products are stored without loss for at least one month (cryogenic oxygen boil-off measured). |
| EC-4 | Energy per kilogram of product measured and published, to size the full plants in M11. |
Workstreams · 5
1
Oxygen from regolith
Split oxygen out of rock, which is about 41–45% oxygen by mass.
- Molten regolith electrolysis (Lunar Resources, Blue Alchemist)
- Carbothermal reduction (Sierra Space) as alternative
- Feedstock from M05 stockpiles
2
Water from ice
Mine icy regolith in a permanently shadowed crater.
- Excavator rated for ~40 K
- Heating in a sealed chamber to release water
- Cold-trap capture and filtration
3
Water processing
Clean water and split it on demand.
- Filtration and contaminant removal
- Electrolysis (ISS OGA heritage)
- Shared tanks with power storage (M04)
4
Storage
Keep the products.
- Liquid oxygen tanks with cryocoolers
- Water tanks kept above freezing
- Boil-off measurement
5
Scale-up data
Measure everything needed to size the full plants.
- kWh per kg O₂ and H₂O
- Electrode and crucible wear
- Feedstock variability
Technology · what we use and how ready it is
| Technology | Used for | Status today | TRL |
|---|---|---|---|
| Molten regolith electrolysis (NASA + Lunar Resources)1 | Oxygen from rock | 2024: 25 kg of simulant processed in vacuum, 0.07 kg O₂/h for 9 h | 4 develop |
| Carbothermal reduction (Sierra Space + NASA)2 | Oxygen from rock (alternative) | Flight-like reactor ran automated in JSC dirty thermal-vacuum chamber (2024); key hardware matured to TRL 6 | 6 |
| Blue Origin Blue Alchemist4 | Oxygen plus silicon, iron, aluminium | Passed CDR Sep 2025; autonomous demo in simulated lunar environment planned 2026 | 5 develop |
| Molten salt electrolysis (Metalysis process, ESA)5 | Oxygen with metal by-product | ESA prototype plant opened 2020; extracts oxygen and leaves a mix of metals | 4 develop |
| ISS Oxygen Generation Assembly6 | Water electrolysis | Flight-proven since 2007; nominal 5.4 kg O₂/day | 9 |
| Ice excavation (NASA Break the Ice)7 | Mining icy regolith | Challenge winners 2024; designs ground-tested | 4 develop |
Components · detailed breakdowns
C06.1
Oxygen-from-regolith pilot plant
7 sub-components · 8 issuesC06.2Ice mining and water extraction plant
6 sub-components · 8 issuesC06.3Liquid oxygen and water storage
6 sub-components · 7 issuesPlan of action
Why this is the most important milestone
- Oxygen is most of the mass a crew uses: for breathing, and as the bulk of rocket propellant.
- Shipping is expensive. At today’s published prices of $1.2M per kg to the surface (see M02), every tonne made locally instead of shipped saves on the order of a billion dollars.
- Rock is mostly oxygen. Lunar rock and soil is about 41–45% oxygen by mass3.
- Polar ice gives water directly. LCROSS found ejecta water “on the order of five percent”10.
How ready are the processes?
| Process | Best demonstration so far | Readiness |
|---|---|---|
| Molten regolith electrolysis | 0.07 kg O₂/h for 9 h from 25 kg simulant, in vacuum, 20241; NASA’s first molecular oxygen from this process9 | TRL 4 |
| Carbothermal reduction | Flight-like reactor, automated, in NASA’s “dirty” thermal-vacuum chamber, 20242 | TRL 6 |
| Blue Alchemist (MRE) | CDR passed Sep 2025; demo planned for 20264 | TRL 5 (estimate) |
| Molten salt electrolysis (Metalysis) | ESA prototype plant (2020); oxygen out, a mix of metals left5 | TRL 4 |
| Water electrolysis | ISS OGA, flight-proven, 5.4 kg O₂/day6 | TRL 9 |
None of the regolith processes has run on the Moon yet. That’s why this is a pilot, and why two different oxygen processes are flown.
Sizing (this plan’s arithmetic)
- Production rate. 10 t of O₂ a year works out to about 1.14 kg/h.
- Power: the big uncertainty.
- NASA’s 2020 study puts a 1.63 kg/h plant at about 26 kW8, roughly 16 kWh per kg of oxygen. On that basis the pilot needs about 18 kW.
- NASA’s 2024 electrolysis demo ran at about 9 kW peak for 0.07 kg/h1. That is about 100 kWh per kg (this plan’s arithmetic from the published figures).
- At demo efficiency, the 26 kW budgeted from M04 would make only about 2 t a year. Reaching 10 t a year would need about 120 kW.
- Demonstration reactors are small and lose most of their heat, so efficiency should improve with size. How much it improves is exactly what this pilot has to measure.
- Who it supports. At 0.895 kg of O₂ per person per day (NASA BVAD, see M09), 10 t a year is enough to breathe for about 30 people. Most of the oxygen will eventually go to propellant instead (M11).
Step-by-step
- Ground-qualify a full-size module of each process on Earth, using simulant matched to the M01 soil data.
- Land the oxygen plant next to the M05 regolith stockpile and connect it to the grid.
- Land the water plant with a cold-rated excavator at the edge of the best PSR from M01.
- Run continuously for six months. Measure output, energy per kg and wear.
- Store and use the products. Liquefy and store oxygen; feed water into the M04 fuel-cell storage and keep a reserve for the crew.
- Publish all the data to size the full plants in M11.
Cost build-up
| Item | Low | High | Basis |
|---|---|---|---|
| Pilot plant development (oxygen + water) | $0.5B | $1.5B | ESTIMATE; Blue Alchemist's 2023 NASA Tipping Point award was $34.7M for an earlier stage [src 11] |
| Delivery of oxygen plant (~3 t, medium lander) | $1.2B | $3.0B | 3 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Delivery of water plant + PSR excavator (~3 t) | $1.2B | $3.0B | 3 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Delivery of tanks, liquefier, electrolyser (~2 t) | $0.8B | $2.0B | 2 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Operations and science, 3 years | $0.1B | $0.3B | ESTIMATE |
| Total | $3.8B | $9.8B | ESTIMATE two pilot plants plus storage; delivery is the largest part |
Mission profile
| Window | 2029–2033 |
| Phase | 1 |
| Depends on | M01, M04, M05 |
| Oxygen plant | Molten regolith electrolysis or carbothermal, ≥10 t O₂/yr |
| Water plant | Excavate icy regolith in a PSR, heat, capture, purify; ≥10 t H₂O/yr |
| Power | 18 kW (NASA study efficiency) to ~120 kW (2024 demo efficiency) for 10 t/yr |
| Storage | Liquid oxygen and water tanks |
| Cost | $3.8–9.8B EST. |
Lowest critical TRL · 4 / 9
Failure modes · 5
FM-1 · Critical
Oxygen-from-rock is only proven at small scale on the ground (0.07 kg/h, ~100 kWh/kg); a 10 t/yr plant needs ~1.1 kg/h and, at demo efficiency, ~120 kWFix: Modular cells; ground-test a full-size module and measure kWh/kg before flight; start at the output the grid can power and add cells as efficiency is proven; run two different processes
FM-2 · Critical
Ice may be scarcer or deeper than hopedFix: Size the water plant from M01 drilling, not orbital estimates; oxygen-from-rock doesn't need ice and covers breathing oxygen
FM-3 · High
Electrode and crucible wear at ~1,600 °C (MRE)Fix: Carry spares; measure wear rates; choose inert anode materials qualified in ground tests
FM-4 · High
Mining equipment must work at about 25–40 K inside PSRsFix: Short excursions from sunlit side; heated electronics; cable power from the grid
FM-5 · Medium
Contaminants in polar ice (CO, NH₃, CH₄, mercury were seen by LCROSS)Fix: Multi-stage purification; treat contaminants as by-products where useful
Sources
- NASA NTRS: Molten regolith electrolysis ground demonstration (ICES 2026) (2026)
- NASA NTRS 20250004151: Carbothermal oxygen production reactor testing (2025)
- WUSTL: Chemical composition of lunar soil ()
- Blue Origin: Blue Alchemist hits major milestone (Sep 2025)
- ESA: ESA opens oxygen plant making air out of moondust (Jan 2020)
- NASA NTRS 20190030425: ISS Oxygen Generation Assembly (2019)
- NASA: Break the Ice Lunar Challenge winners (Jun 2024)
- Colozza, NASA/CR: ISRU plant power (1.63 kg/h O₂ at 25.83 kW) (Mar 2020)
- NASA Kennedy: NASA Kennedy breathes life into Moon soil testing (2025)
- NASA M2M-30044 Lunar Surface Data Book (2025)
- NASA: 2023 NASA Tipping Point selections (Jul 2023)