PLAN REV 1.2MILESTONES 14COMPONENTS 26UPDATED 2026-11-17LICENSE CC BY-SA 4.0
Plan / Phase 1 / M04
M04 · Phase 1 · 2028–2032

Surface power grid

Build a hybrid power grid of tall solar towers on the sunlit ridges, a fission reactor for darkness, energy storage and high-voltage cables, sized to run the oxygen plant and the first habitat.
Objective

Deliver at least 100 kW of solar peak power and at least 40 kWe of continuous fission power, connected by a high-voltage DC grid, so the base never loses essential power, even during the longest polar darkness.

Exit criteria · what "done" means
#Criterion
EC-1At least 100 kW solar peak power installed on at least two separate ridge points.
EC-2Fission unit delivering at least 40 kWe continuously for six months.
EC-3Essential loads (comms, heaters, life support standby) never lose power across the longest darkness period recorded at the site.
EC-4Grid survives loss of any single power source without dropping essential loads.
EC-5Cable-laying rover has laid at least 3 km of cable.
Workstreams · 6
1

Solar towers

Tall, sun-tracking arrays that see over the terrain.

  • 10 kW VSAT, ~10 m mast
  • 50 kW VSAT-XL, 34 m tall
  • Spread across 2–3 ridge points
2

Fission power

Continuous power regardless of sunlight.

  • HALEU fuel, closed Brayton or Stirling
  • Placed 1–3 km away, behind terrain
  • Remote start after landing
3

Storage

Ride through solar gaps and peaks.

  • Regenerative fuel cells (320–650 Wh/kg)
  • Li-ion for fast peaks (~160 Wh/kg)
  • Shares water and gas tanks with ISRU
4

Grid and cables

Move power between sources and users.

  • ±4 kVDC aluminium cable
  • DC-DC converters at each user
  • Separate habitat and ISRU microgrids
5

Cable laying

Robots lay and bury cable.

  • LunaGrid-Lite-style rover reels out cable
  • Shallow trench or regolith cover
  • Fault location by time-domain reflectometry
6

Control

Automatic load management.

  • Priority load shedding
  • Remote operation from Earth
  • Fault isolation
Technology · what we use and how ready it is
TechnologyUsed forStatus todayTRL
Kilopower / KRUSTY fission test5Heritage for the reactor28-hour nuclear system test 2018 at various power levels; Stirling converters worked 5
US Lunar Reactor-1 (SPARC)6Reactor procurement pathDraft solicitation Aug 2026: ≥20 kWe, ≥5 yr, HALEU, closed Brayton, <15 t. No award yet 5
Vertical Solar Array Technology (VSAT)410 kW-class solar towersThree NASA prototype contracts (2022); deploy to ~10 m 6
Astrobotic VSAT-XL750 kW towersNASA SBIR study award 2024; 34 m tall; Redwire ROSA arrays. Phase II follow-on Jun 2025–Jun 2027 5 develop
Astrobotic LunaGrid-Lite8Cable-laying rover and power transfer1 kW; ~500 m of cable in the 2025 design (1 km in earlier plans); passed CDR Aug 2025 6
Regenerative fuel cells9Night and gap storageNASA Glenn breadboard ran 550+ hours of simulated lunar cycles (open-loop) 5 develop
High-voltage DC lunar cable2Power transmissionNASA Glenn analysis: ±4 kVDC Al cable best for 3 km at 95% 5
Components · detailed breakdowns
Plan of action

How much power does a base need?

NASA studies give concrete numbers:

Load Power Source
Oxygen plant making 1.63 kg/h of O₂ 25.83 kW Colozza (NASA)10
Six-person base camp 28.05 kW Colozza10
Habitat, 4 crew, 30+ days 20–50 kW Csank & Scott (NASA)1
ISRU at scale 60+ kW Csank & Scott1
Growth path 1–5 → 10–20 → 80–100 kW Csank & Scott1

This milestone targets about 140 kW of total capacity: 100 kW of solar peak plus 40 kWe of fission. That’s enough for the oxygen pilot plant (M06) and the first habitat (M08), with room to grow.

Why not just solar, or just batteries?

  • Sunlight. The best points on the ridge connecting Shackleton and de Gerlache craters are sunlit 92.27% of the time at 2 m height and 95.65% at 10 m11. Shadow periods still happen, and NASA cites intermittent darkness of up to about 100 hours at the pole1.
  • Storage maths (this plan’s arithmetic):
    • Keeping 30 kW of essential load alive for 100 hours takes 3 MWh.
    • Li-ion stores about 160 Wh/kg, so that’s about 19 t of batteries1.
    • Regenerative fuel cells store 320–650 Wh/kg1, which cuts it to about 5–9 t.
    • Either way, that much storage is heavy to land.
  • Fission. A 40 kWe reactor of about 10 t (NASA’s reference design1) gives continuous power for 10 years. For long darkness it’s the lightest answer, and it lets solar handle peaks.

The reactor: what’s real today

  • KRUSTY (2018). NASA and DOE ran a real fission reactor with Stirling converters for 28 hours straight, at various power levels5.
  • NASA reference design. 40 kWe, about 10 t, four pairs of Stirling engines, sodium heat pipes, 10-year life1.
  • Moving target. The US programme has changed requirements several times: 40 kWe in 20221, then at least 100 kWe with closed Brayton conversion in 202512. In 2026 it settled on “Lunar Reactor-1”: at least 20 kWe, at least 5 years, HALEU fuel, under 15 t614. No contract has been awarded yet. Open Moon’s grid is designed to accept any unit from 20 to 100 kWe.

Solar towers

  • VSAT. NASA funded three prototypes in 2022 for $19.4M in total; they deploy to about 10 m4. Each is a 10 kW-class array20.
  • VSAT-XL. Astrobotic’s design is 50 kW and 34 m tall, using Redwire roll-out arrays7. NASA then gave it an SBIR Phase II contract running from June 2025 to June 20271718.
  • Why height matters. Taller masts see over the horizon and catch more hours of sun11.

Cables

  • Voltage choice. NASA Glenn found that about ±4 kVDC aluminium cable gives the lightest 3 km link at 95% efficiency2.
  • Why not beam power wirelessly? Power beaming was 13–27% efficient and would need 30–60 t of extra generating capacity to make up the losses2.
  • Cable mass. NASA estimates the cable itself at only about 240 kg for 3 km at 2,800 V15. Because the reactor is heavy (about 0.25 kg per watt), the line must be efficient: any power lost in the cable has to be made up with extra generating capacity2.
  • Laying the cable. Astrobotic’s LunaGrid-Lite is designed to transmit 1 kW; its 2025 design lays about 500 m of cable8. NASA’s 2023 award described 1 km19.

Where the money goes

About 85% of this milestone’s cost is delivery, not hardware. Two things change that:

  1. Cheaper heavy cargo landers (M02).
  2. Making power hardware on the Moon. Blue Origin’s Blue Alchemist has made solar cells and wire from regolith simulant13. Scaling that up is part of M12.

Step-by-step

  1. First landing (small lander): a 10 kW VSAT, a LunaGrid-Lite-class cable rover, and the LTE kit from M03.
  2. Second 10 kW VSAT on a second ridge point, with a cable link between the two.
  3. Two 50 kW VSAT-XL towers on medium landers.
  4. Regenerative fuel cell storage, sharing tanks with the M06 water plant.
  5. Fission unit on a heavy lander. Rovers set it 1–3 km from the habitat zone behind terrain, then it starts remotely.
  6. Close the grid so it survives losing any single source.
Cost build-up
ItemLowHighBasis
2 × 10 kW vertical solar arrays (hardware)$0.05B$0.15BESTIMATE; NASA's three VSAT prototypes cost $19.4M in total [src 4]
Delivery of 10 kW arrays (~2 t, small landers)$1.2B$2.4B2 t × $0.6–1.2M/kg (mass ESTIMATE)
2 × 50 kW VSAT-XL towers (hardware)$0.1B$0.3BESTIMATE
Delivery of VSAT-XL (~6 t, medium landers)$2.4B$6.0B6 t × $0.4–1.0M/kg (mass ESTIMATE)
40 kWe fission unit (develop, build, qualify)$1.0B$3.0BESTIMATE; Congress gave $250M for Fission Surface Power in FY2026 alone [src 16]
Delivery of fission unit (~10 t, heavy lander)$2.0B$6.0BNASA reference design ~10 t for 40 kWe [src 1] × $0.2–0.6M/kg
Regenerative fuel cell storage, ~3 MWh (hardware)$0.05B$0.15BESTIMATE
Delivery of storage (~3 t, medium lander)$1.2B$3.0B3 MWh ÷ ~500 Wh/kg ≈ 6 t at cell level; ~3 t assumes partial reuse of ISRU tanks (ESTIMATE) × $0.4–1.0M/kg
Cables, converters, switchgear (hardware)$0.05B$0.15BESTIMATE
Delivery of grid hardware (~1 t: ~5 km of cable, converters, switchgear)$0.4B$1.0BNASA estimates ~240 kg of cable for 3 km at 2,800 V [src 15]; rest ESTIMATE; × $0.4–1.0M/kg
Integration, testing, operations$0.1B$0.3BESTIMATE
Total$8.6B$22.5BESTIMATE about 85% of this is delivery cost; see the analysis below

Mission profile

Window2028–2032
Phase1
Depends onM00, M02, M03
Solar2 × 10 kW VSAT + 2 × 50 kW VSAT-XL towers
Fission1 × 40 kWe-class reactor (ref. design ~10 t)
StorageRegenerative fuel cells, ~3 MWh
Grid±4 kVDC aluminium cables, 1–3 km
Load at endOxygen pilot plant ~26 kW + habitat 20–50 kW
Cost$8.6–22.5B EST.
Lowest critical TRL · 5 / 9

Failure modes · 6

FM-1 · Critical
Darkness: even the best ridges have shadow periods; NASA cites up to ~100 h at the pole, and 354 h is the design night for the US reactor
Fix: Fission base load + solar on multiple ridge points + storage; never rely on one source
FM-2 · Critical
The US lunar reactor's requirements keep changing (40 → 100 → 20 kWe) and no contract has been awarded
Fix: Design the grid for any 20–100 kWe unit; buy from whichever programme flies first; solar-only fallback with more storage
FM-3 · High
Delivery cost dominates: ~85% of this milestone is shipping mass
Fix: Push heavy-cargo pricing down; make cables and later solar cells from regolith (Blue Alchemist, M12)
FM-4 · High
Dust on arrays and radiators
Fix: Vertical arrays shed dust; keep 1 km+ from landing pads; landing pads in M05
FM-5 · High
Reactor radiation near crew
Fix: 1–3 km separation, terrain or berm shielding; US draft sets ≤5 rem/yr at 1 km
FM-6 · Medium
Cable damage from rovers, thermal cycling and micrometeoroids
Fix: Bury or cover cables; redundant routes; fault-locating electronics

Sources

  1. Csank & Scott, NASA GRC: Power and Energy for the Lunar Surface (Apr 2022)
  2. NASA NTRS 20220002315: Lunar power transmission for fission surface power (2022)
  3. SpaceNews: NASA and DOE to collaborate on lunar nuclear reactor development (Jan 2026)
  4. NASA RELEASE 22-090: Vertical Solar Array Technology awards (Aug 2022)
  5. Poston et al.: Results of the KRUSTY nuclear system test (2020)
  6. NewSpace Economy: What NASA's SPARC procurement reveals about Lunar Reactor-1 (secondary) (Sep 2026)
  7. Astrobotic: awarded lunar power study with VSAT-XL (Aug 2024)
  8. Astrobotic: LunaGrid-Lite completes critical design review (2025)
  9. NASA NTRS 20260002730: Regenerative fuel cell lunar cycle testing (Apr 2026)
  10. Colozza, NASA/CR: Small lunar base camp and ISRU power (Mar 2020)
  11. Gläser et al. 2014, Icarus: Illumination at the lunar south pole (2014)
  12. NASA: NASA seeks industry feedback on fission surface power (Aug 2025)
  13. Blue Origin: Blue Alchemist powers our lunar future (Feb 2023)
  14. Scientific American: White House plan for lunar nuclear power (NSTM-3) (Apr 2026)
  15. Oleson et al., NETS 2022: deployable 40 kWe fission surface power concept (NTRS 20220004670) (2022)
  16. SpacePolicyOnline: Great news for NASA in the House-Senate FY2026 appropriations report (Jan 2026)
  17. Astrobotic: Astrobotic developing XL solar array tech for lunar power infrastructure (SBIR Phase II) (Jul 2025)
  18. USAspending: NASA contract 80NSSC25C0032, Phase II SBIR VSAT-XL (Jun 2025)
  19. NASA: 2023 NASA Tipping Point selections (Jul 2023)
  20. NASA GCD annual review: Vertical Solar Array Technology (VSAT) project (Sep 2023)