Plan / Phase 1 / M02
M02 · Phase 1 · 2027–2031
Transport to the surface
Secure reliable rides for cargo of every size and for crews. Open Moon buys transport; it does not build rockets.
Objective
Establish contracts and interfaces for three cargo classes (under 1 t, about 3 t, about 15 t) and for crew seats, so every later milestone can count on a delivery schedule. Build the equipment to offload cargo on the surface.
Exit criteria · what "done" means
| # | Criterion |
|---|---|
| EC-1 | Firm delivery contracts or reservations for at least two independent providers in each cargo class. |
| EC-2 | A published Open Moon payload interface standard (mechanical, electrical, data) that fits all selected landers. |
| EC-3 | An offloading crane delivered and tested on the surface, able to lift cargo from a lander deck to the ground. |
| EC-4 | Crew transport agreement in place for Phase 2 sorties. |
Workstreams · 6
1
Small cargo (under 1 t)
Buy rides on commercial landers for instruments and small robots.
- Firefly Blue Ghost
- Astrobotic Griffin
- Intuitive Machines Nova-C
- Two providers per payload where possible
2
Medium cargo (about 3 t)
Rovers, power units and pilot plants.
- Blue Origin Blue Moon Mark 1 (up to 3 t)
- Track Pathfinder flight (NET Q1 2027)
3
Heavy cargo (about 15 t)
Habitats, reactors and large ISRU plants.
- Starship cargo variant
- Blue Moon Mk2 cargo variant
- NASA states ~15 t per cargo landing
4
Crew access
Seats for Open Moon crews.
- Partnership with NASA Moon Base / Artemis
- Commercial HLS seats once offered
- Crew training and medical certification
5
Offloading and handling
Getting cargo off tall landers safely.
- Cable-driven crane (LSMS heritage)
- Ramps and winches
- Payload carts towed by LTVs
6
Interfaces
One standard so payloads fit any lander.
- Mechanical bolt pattern and loads
- Power and data connectors
- Thermal and dust covers
Technology · what we use and how ready it is
| Technology | Used for | Status today | TRL |
|---|---|---|---|
| Firefly Blue Ghost lander1 | Small cargo | Fully successful landing Mar 2025; 14 days of operations | 9 |
| Intuitive Machines Nova-C2 | Small cargo | Landed twice (2024, 2025); both times ended on its side | 7 |
| Astrobotic Griffin2 | Small cargo | First flight planned January 2027 | 6 |
| Blue Origin Blue Moon Mark 13 | Medium cargo (up to 3 t) | Pathfinder to Shackleton connecting ridge NET Q1 2027 | 6 |
| SpaceX Starship HLS / cargo4 | Heavy cargo and crew | Starship reached orbit on flights 14 and 15 (2026); ship caught by the tower after flight 15 | 6 |
| Blue Origin Blue Moon Mk25 | Crew; cargo variant | ~$3.1B NASA contract; uncrewed demo expected Feb 2029 | 5 |
| Lunar Surface Manipulation System (LSMS)7 | Offloading crane | Ground prototypes tested; NASA proposed path to TRL 6 | 4 develop |
Components · detailed breakdowns
C02.1
Common payload interface
6 sub-components · 7 issuesC02.2Offloading crane
6 sub-components · 7 issuesPlan of action
Where transport stands (November 2026)
- Artemis II flew four astronauts around the Moon on 1–10 April 202613.
- Artemis III is now a 2027 test in Earth orbit. Orion will dock with Starship and Blue Moon test articles there. The first crewed landing is Artemis IV, planned for 202810.
- NASA plans at least one landing a year after Artemis III, then a crewed landing every six months after Artemis V12.
- CLPS 2, a 10-year contract worth up to $10B in total, was awarded to eight companies in November 202611.
- Bottom line: there is a growing commercial market to buy rides from.
How much does it cost to land a kilogram?
- Published price: Astrobotic lists $1.2M per kg to the surface8.
- Cost growth: NASA’s first eight CLPS delivery orders grew nearly 26% in total value and slipped 14 months on average9.
- Heavy landers: NASA expects cargo landers to carry about 15 t each6. We found no published price for them. This plan assumes $0.2–0.6M per kg (ESTIMATE) and shows that assumption wherever it’s used.
This is the single most important number in the plan. Every kilogram made on the Moon instead of shipped saves hundreds of thousands of dollars, which is why ISRU (M06, M11, M12) gets priority.
Step-by-step
- Publish the payload interface standard: bolt pattern, loads, power and data connectors. Every Open Moon payload uses it.
- Reserve small-lander rides for M01 and M03 payloads, with two providers per critical payload.
- Book medium-lander slots on Blue Moon Mark 1 (up to 3 t3) for rovers, pilot plants and the first power units. Watch the Pathfinder flight, planned no earlier than Q1 2027.
- Negotiate heavy-cargo slots for habitats and the reactor. Starship reached orbit on flights 14 and 15 in 20264, but ship-to-ship propellant transfer has never been done5 and was still listed as an upcoming test in October 20266. Every heavy item has a fallback design that splits into medium-lander pieces.
- Build and land the offloading crane. It’s based on NASA’s LSMS cable-driven crane, which has been tested on the ground7.
- Sign a crew transport agreement for Phase 2.
Cost build-up
| Item | Low | High | Basis |
|---|---|---|---|
| Common payload interface and integration team (5 years) | $0.15B | $0.4B | ESTIMATE |
| Surface offloading crane ×2 (LSMS-class) | $0.1B | $0.3B | NASA proposed a $22M Phase I to reach a TRL 6 proto-flight LSMS [src 7]; flight units and delivery added (ESTIMATE) |
| Delivery of 2 cranes (~1 t total) on small/medium landers | $0.6B | $1.2B | 1 t × $0.6–1.2M/kg (ESTIMATE; $1.2M/kg is Astrobotic's published price) |
| Schedule and cost-growth reserve (30%) | $0.1B | $0.3B | Total value of NASA's first eight CLPS task orders grew nearly 26% [src 9] |
| Total | $0.95B | $2.2B | ESTIMATE interfaces, offloading and integration only; each delivery is costed in the milestone that uses it |
Mission profile
| Window | 2027–2031 |
| Phase | 1 |
| Depends on | M00 |
| Small cargo | Under 1 t: commercial landers (Blue Ghost, Griffin, Nova-C) |
| Medium cargo | About 3 t: Blue Moon Mark 1 |
| Heavy cargo | About 15 t: Starship and Blue Moon Mk2 cargo variants |
| Crew | Seats via NASA Artemis / Moon Base partnership or commercial HLS |
| Cost | $0.95–2.2B EST. |
Lowest critical TRL · 6 / 9
Failure modes · 5
FM-1 · Critical
Heavy cargo landers are not yet proven: Starship has not demonstrated orbital refuelling, and Blue Moon Mk2's demo is expected in 2029Fix: Keep everything in Phases 0–1 within small and medium lander sizes; design heavy items to split across two providers; set schedule margin of 2+ years
FM-2 · High
Landing reliability: of four CLPS missions in 2024–25, two landers tipped over and one never attempted a landingFix: Fly critical items twice; prefer providers with upright landings; insure or hold spares
FM-3 · High
Cost and schedule growth: CLPS orders grew nearly 26% in total value and slipped 14 months on averageFix: Budget 30% growth on every delivery; plan for slips in the schedule
FM-4 · Medium
Tall landers (Starship) put cargo many metres above the groundFix: Crane or elevator on the lander; LSMS-style cable crane on the surface
FM-5 · Medium
Crew seats depend on government programmesFix: Partner with NASA Moon Base; keep commercial-seat option open
Sources
- Firefly: Blue Ghost completes 14 days of surface operations (Mar 2025)
- Commercial Lunar Payload Services, Wikipedia (accessed Nov 2026)
- Blue Origin: Blue Moon Mark 1 (accessed Nov 2026)
- Starship flight 15, Wikipedia (Nov 2026)
- NASA OIG IG-26-004: Management of the Human Landing System contracts (Mar 2026)
- NASA HLS IAC 2026 presentation (cargo landers ~15 t) (Oct 2026)
- NASA NTRS: LSMS technology overview (2020)
- Astrobotic Lunar Landers Payload User's Guide ($1.2M/kg) (Aug 2021)
- NASA OIG IG-24-013: CLPS initiative (Jun 2024)
- NASA: NASA Shares Plans to Accelerate Artemis, Return to Moon (Nov 2026)
- NASA: NASA Awards Moon Base Transportation, Technology, Science Projects (CLPS 2) (Nov 2026)
- NASA: NASA Unveils Initiatives to Achieve America's National Space Policy (Mar 2026)
- NASA: Artemis II mission milestones, an image and video recap (Apr 2026)