PLAN REV 1.2MILESTONES 14COMPONENTS 26UPDATED 2026-11-17LICENSE CC BY-SA 4.0
C02.2 · Component of M02

Offloading crane

A lightweight, cable-driven crane based on NASA's LSMS that lifts cargo off a lander deck and sets it on the ground. It can also dig, act as a forklift and position payloads around the base.
Sub-components · 6
1

Base and self-leveling turret

Holds the crane to a lander deck or rover and keeps it level on slopes or on a tilted lander.

  • Mounting frame to C02.1 pallet hard points
  • Waist rotation bearing and drive
  • Self-leveling legs or wedges (±15°)
  • Launch locks
  • Counterweight bay (filled with regolith on the surface)
BASIS: LSMS proposal: self-leveling base · TRL 4
2

Boom links

Lightweight truss links carry loads mainly in tension and compression, not bending, which saves mass.

  • Shoulder link (~4 m)
  • Elbow link (~4 m)
  • Wrist link (~4 m)
  • Spreader bars that guide the cables
  • Hinges with passive structural cables
BASIS: LSMS truss-and-cable architecture · TRL 4
3

Cable actuators

Motors on the base reel cables in and out to move each joint, so no heavy gearboxes sit out on the arm.

  • Cable spools and winch motors at the base
  • Low-temperature gearboxes
  • Pulleys and cable routing
  • Cable tension and length sensors
  • Brakes that hold on power loss
BASIS: LSMS cable actuation; JPL bulk-metallic-glass cold gearbox (option) · TRL 4
4

End effectors

A quick-change wrist lets the crane switch tools without an astronaut.

  • Hook and hoist with spreader bar
  • Forklift tines for C02.1 pallets
  • Regolith bucket
  • Quick-change tool interface
  • Power connector at the tip for recharging a rover
BASIS: LSMS end-effector toolbox; Honeybee quick-change · TRL 4
5

Sensing and control

Cameras and a pose estimator find the payload, and software plans cable motions so the load follows a safe path.

  • Pose estimator and cameras
  • Joint angle encoders
  • Load cell at the hoist
  • Trajectory-tracking software
  • Teleoperation link via the base network
BASIS: ULTOR pose estimator (LSMS field tests); NASA LSMS trajectory tracking · TRL 4
6

Power and thermal

Runs from the lander or base grid during lifts and keeps its motors and electronics warm between jobs.

  • 28 V DC power input (C02.1 interface)
  • Small battery for safe-stow on power loss
  • Survival heaters on motors and electronics
  • Multi-layer insulation on the base box
  • Dust seals on bearings
BASIS: Standard lander-hosted payload practice · TRL 5
Engineering notes

What it does

Landers put cargo on a deck several metres above the ground. Something has to lift it down. This crane does that job. It also moves cargo around the landing zone, loads pallets onto carts and digs regolith. It is based on NASA Langley’s Lightweight Surface Manipulation System (LSMS), a family of cable-driven cranes that has been developed and field-tested on Earth.

How it works

  • Why cables. The LSMS uses truss links moved by cables. The structure works in tension and compression rather than bending, which gives a better mass and power ratio than a conventional robotic arm1. All motors sit at the base3.
  • Heritage. A 1,000 kg-class LSMS prototype was field-tested at Moses Lake, Washington, in 2008. It demonstrated offloading, forklift mode, digging and a quick-change tool1. The family runs from the LSMS-L35 (35 kg lift in lunar gravity, sized for CLPS landers) to the LSMS-1000 (1,000 kg, sized for Blue Moon)3.
  • Proto-flight design. NASA’s proto-flight version reaches about 7.6 m (25 ft) and lifts about 1 t. It has a power connection at the tip that could recharge a rover. Its tools include a bucket, forklift tines and a welder2. A mini version with about 1.8 m (6 ft) reach suits small landers2.
  • NASA’s proposed path. A 3-year, $22M Phase I would build an engineering unit and a proto-flight unit. It targets a 500 kg mass goal, ±15° self-leveling, self-deployment and a 2-week mission. That would take components from TRL 3 to 5 and the system from TRL 4 to 61. The proposal drawing shows three links of about 4 m each1.
  • Comparison. The best planetary offload so far is InSight’s 1.8 m arm, which moved a 29 kg seismometer once1.
  • Our use. Crane 1 is mounted on the deck of a Blue Moon Mk1 delivery. That lander is 8.05 m tall4. Crane 1 lifts the other cargo down, then lifts Crane 2 down onto a mobile base. LSMS plans already show offloading from a mobility vehicle1. For Starship, whose crew area is at the top of a 52 m vehicle with an elevator5, the elevator brings cargo down and the mobile crane takes it from there.

Sizing

Load at the hook (arithmetic, lunar gravity 1.62 m/s²6):

Quantity Value Working
Rated lift 1,000 kg LSMS-1000 class3
Weight on the Moon 1,620 N 1,000 × 1.62
Moment at 7.6 m reach ~12.3 kN·m 1,620 × 7.6
Same weight on Earth ~165 kg 1,620 ÷ 9.81
Payload-to-crane mass ratio 2 : 1 1,000 ÷ 500 kg goal1
Two cranes delivered ~1,000 kg 2 × 500 kg (matches M02 budget)

The fourth row matters for testing. On Earth, a 165 kg test mass loads the crane the way a full 1 t payload does on the Moon. The crane’s own weight is six times higher on Earth, though, so ground tests need a gravity-offload rig.

Testing and qualification

  1. Component tests. Cycle cables, spools, brakes and gearboxes in thermal vacuum down to the south-pole design low of −180 °C used by NASA’s VSAT project7, with lunar dust simulant present.
  2. Engineering unit. Build the full-size crane. Run lifts with a 165 kg test mass at full reach on a gravity-offload rig. Test self-leveling on a ±15° tilt table.
  3. Field test. Offload a full-size lander deck mock-up and C02.1 pallets outdoors, as the 2008 Moses Lake tests did1.
  4. Proto-flight unit. Run vibration, acoustic and thermal-vacuum tests to the lander environment, then a fit check on the lander.
  5. On the Moon. Deploy from stowage and lift a dummy mass, then the real cargo. Measure cable wear and dust after every lift.

Open questions

  • Astrobotic is to provide a cargo accommodation system for Blue Moon4. Will it include an offloader? If so, could this crane be simplified?
  • Which cable material keeps its strength and abrades least in lunar dust at −180 °C?
  • Should the mobile crane ride on an LTV (M07), or on its own powered cart?
  • How do we certify a crane for lifting near crew, and what proof-load factor should we use?
Problems and solutions · 7
SeverityProblemSolution
CriticalOnly ground prototypes exist; no LSMS has flownFund the proto-flight unit and a full environment test campaign first. Keep simple backups (ramps and winches) for the first deliveries.
HighCables, pulleys and bearings jam or wear in abrasive lunar dust and deep coldSeal the bearings and spools at the base, test cables in dust and thermal-vacuum chambers, and design cables to be replaced robotically.
HighA tipped or sloped lander puts the crane far off levelSelf-leveling base (±15°). If the lander leans more than that, the mobile crane offloads it from the ground.
HighA load swings or drops and damages the payload or the landerLift slowly with a load cell and pose camera. Brakes hold on power loss. Proof-load test before every first lift of a new payload type.
MediumStarship decks are far higher than the crane can reachUse the lander's own elevator to bring cargo to the ground, then let the crane move it from there.
MediumIntegration with each lander's structure and avionics is not yet designedMount the crane through the C02.1 pallet hard points and connector, so integration is the same as for any other payload.
MediumA 1 t limit cannot lift a whole 3 t Blue Moon Mk1 payload in one pieceSplit medium cargo into pieces of 1 t or less, or use the lander's own offloading system for single heavy items.

Specification

HeritageNASA Langley Lightweight Surface Manipulation System (LSMS)
Lift capacity1,000 kg in lunar gravity (LSMS-1000 class)
Reach~7.6 m (25 ft, NASA proto-flight design)
Mass~500 kg each (NASA proposal mass goal)
Peak load moment~12.3 kN·m at full reach and full load (arithmetic)
LevelingSelf-leveling base, ±15°
ToolsHook/hoist, forklift tines, regolith bucket, quick-change wrist
Quantity2 (one lander-mounted, one on a mobile base)
Delivery classMedium lander (Blue Moon Mk1), ~1 t for both
Technology readiness · TRL 4 / 9

Sources

  1. NASA NTRS: LSMS technology overview (Jones, for Blue Origin) (Aug 2020)
  2. NASA: Lightweight crane technology could find a home on the Moon (Feb 2021)
  3. NASA NTRS: Trajectory tracking for the LSMS family of cable-driven cranes (2024)
  4. Blue Moon (spacecraft), Wikipedia (accessed Nov 2026)
  5. NASA HLS IAC 2026 presentation (Oct 2026)
  6. NASA NSSDC: Moon fact sheet (accessed Nov 2026)
  7. NASA NTRS: Vertical Solar Array Technology annual review (south pole thermal environment) (Sep 2023)
ProjectOPEN MOON · Self-sustaining lunar colony