PLAN REV 1.2MILESTONES 14COMPONENTS 26UPDATED 2026-11-17LICENSE CC BY-SA 4.0
Programme budget

Costs

How much each milestone costs and how those numbers were built. Every line shows its basis.

Programme total: $122B to $367B ESTIMATE, in today's US dollars, spread across the milestone windows. Costs are built bottom-up from published contract values and programme costs wherever they exist, and from delivered-mass × price-per-kg where they don't. Each milestone page shows the line items and the basis for every one.

These are planning estimates, not quotes. Space programmes routinely overrun; NASA's own OIG has documented large overruns on SLS, Orion and OSAM-1. The high column includes margin for that, but real costs could still be higher. Where a figure is a contract ceiling, the actual spend may be lower.

Delivery pricing used throughout the plan: small landers (under 1 t) at up to $1.2M per kg landed, Astrobotic's published price [benchmark]. Medium (about 3 t, Blue Moon Mark 1 class) and large (about 15 t) landers have no published price, so the plan assumes $0.4M–$1.0M per kg for medium and $0.2M–$0.6M per kg for large (ESTIMATE) and shows this assumption on every line that uses it. If heavy-cargo prices fall as SpaceX and Blue Origin claim, the totals drop sharply; if not, they rise.

Benchmarks we price against

BenchmarkFigureSource
ISS design, development and buildMore than $100BNASA, Ignition release (Mar 2026)
ISS operating costAbout $3B per yearNASA OIG IG-22-005 (Nov 2021)
ISS commercial resupply, CRS-1$191.3M per flight, about $63,200 per kg of upmassNASA OIG IG-18-016 (Apr 2018)
ISS commercial resupply, CRS-2 (projected)$300.6M per flight, about $71,800 per kgNASA OIG IG-18-016 (Apr 2018)
Artemis spending FY2012–FY2025 (projection)$93B; $4.1B per SLS/Orion launchNASA OIG IG-22-003 (Nov 2021)
NASA total budget FY2026 (regular appropriation)$24.438B, of which Exploration $7.783BCRS R43419 (Jun 2026)
Lunar Terrain Vehicle task orders (2026)Astrolab $219M, Lunar Outpost $220MNASA RELEASE26-046 (May 2026)
Rover delivery to the south pole (Blue Origin)$188M plus $280.4M option, for two rovers in 2028NASA RELEASE26-046 (May 2026)
VIPER delivery (CLPS CS-7, Blue Origin)Up to $190MNASA release (Sep 2025)
Lunar relay services (Intuitive Machines)Up to $4.82B maximum contract valueNASA release (Sep 2024)
ESA Moonlight phase 1 (Telespazio)€123MEuropean Spaceflight (Mar 2025), reporting the Oct 2024 ESA contract
ICON Project Olympus construction R&D$57.2M SBIR Phase IIIICON (Nov 2022)
Blue Alchemist (oxygen and solar cells from regolith)$34.7M NASA Tipping PointNASA, 2023 Tipping Point selections (Jul 2023)
Published price to the lunar surface (Astrobotic)$1.2M per kg to the surface; $300k per kg to lunar orbitAstrobotic Payload User's Guide v5.0 (Aug 2021)
CLPS delivery task orders, cost growthEight orders grew from $781.4M to $984.3M (+26%); average delay 14 monthsNASA OIG IG-24-013 (Jun 2024)
Human Landing System programme$6.9B obligated since 2019; $18.3B estimated through FY2030NASA OIG IG-26-004 (Mar 2026)
Large cargo lander classAbout 15 t (33,000 lb) per cargo landingNASA HLS IAC 2026 presentation (Oct 2026)
NASA Moon Base (reported)About $20B over 7 years; $6B for expanded CLPS over a decadePlanetary Society, citing NASA documents (2026)
CLPS 2 contract vehicle10-year IDIQ, $10B combined ceiling, 8 companiesNASA (Nov 2026)
Vertical Solar Array Technology prototypes$19.4M total across three companies (2022)NASA RELEASE 22-090 (Aug 2022)
Falcon Heavy list price$97M (raised from $90M in Mar 2022)Space.com (Mar 2022)

By milestone

M00 · Programme set-up and site selection · $0.05–0.15B

ItemLowHighBasis
Core engineering team, 2 years$0.04B$0.11BESTIMATE: 60–150 full-time staff at ~$350k loaded cost per year
Computing, data processing, illumination modelling$0.005B$0.02BESTIMATE
Legal, international coordination$0.005B$0.02BESTIMATE

M01 · Robotic prospecting and ground truth · $0.5–1.2B

ItemLowHighBasis
Prospecting rover ×2 (design, build, test)$0.2B$0.5BESTIMATE. Smaller than LTV-class rovers, whose task orders are $219–220M each [benchmark]
Delivery to the south pole ×2$0.25B$0.5BVIPER delivery task order up to $190M each (CS-7); range covers price growth
Operations, science team, data release$0.05B$0.2BESTIMATE

M02 · Transport to the surface · $0.95–2.2B

ItemLowHighBasis
Common payload interface and integration team (5 years)$0.15B$0.4BESTIMATE
Surface offloading crane ×2 (LSMS-class)$0.1B$0.3BNASA proposed a $22M Phase I to reach a TRL 6 proto-flight LSMS [src 7]; flight units and delivery added (ESTIMATE)
Delivery of 2 cranes (~1 t total) on small/medium landers$0.6B$1.2B1 t × $0.6–1.2M/kg (ESTIMATE; $1.2M/kg is Astrobotic's published price)
Schedule and cost-growth reserve (30%)$0.1B$0.3BTotal value of NASA's first eight CLPS task orders grew nearly 26% [src 9]

M03 · Communications, navigation and time · $0.72–1.94B

ItemLowHighBasis
Relay and ground-station service fees, 5 years$0.15B$0.5BESTIMATE. NASA's relay contract has a maximum potential value of $4.82B [src 1]
Backup relay smallsat ×1 (build + launch to lunar orbit)$0.15B$0.4BESTIMATE; ~300 kg at $300k/kg to lunar orbit ≈ $90M delivery [src 8] plus spacecraft
Surface LTE base station, mesh radios, rim relay masts$0.05B$0.15BESTIMATE hardware
Delivery of base comms node and rim relay masts (~400 kg)$0.24B$0.48B~220 kg comms node (C03.1) + rim masts (C03.2), ESTIMATE × $0.6–1.2M/kg ($1.2M/kg published [src 8])
Optical terminal for the base (high-rate Earth link)$0.08B$0.25BESTIMATE; based on O2O/LCRD class terminals
Operations and network engineering, 5 years$0.05B$0.16BESTIMATE

M04 · Surface power grid · $8.6–22.5B

ItemLowHighBasis
2 × 10 kW vertical solar arrays (hardware)$0.05B$0.15BESTIMATE; NASA's three VSAT prototypes cost $19.4M in total [src 4]
Delivery of 10 kW arrays (~2 t, small landers)$1.2B$2.4B2 t × $0.6–1.2M/kg (mass ESTIMATE)
2 × 50 kW VSAT-XL towers (hardware)$0.1B$0.3BESTIMATE
Delivery of VSAT-XL (~6 t, medium landers)$2.4B$6.0B6 t × $0.4–1.0M/kg (mass ESTIMATE)
40 kWe fission unit (develop, build, qualify)$1.0B$3.0BESTIMATE; Congress gave $250M for Fission Surface Power in FY2026 alone [src 16]
Delivery of fission unit (~10 t, heavy lander)$2.0B$6.0BNASA reference design ~10 t for 40 kWe [src 1] × $0.2–0.6M/kg
Regenerative fuel cell storage, ~3 MWh (hardware)$0.05B$0.15BESTIMATE
Delivery of storage (~3 t, medium lander)$1.2B$3.0B3 MWh ÷ ~500 Wh/kg ≈ 6 t at cell level; ~3 t assumes partial reuse of ISRU tanks (ESTIMATE) × $0.4–1.0M/kg
Cables, converters, switchgear (hardware)$0.05B$0.15BESTIMATE
Delivery of grid hardware (~1 t: ~5 km of cable, converters, switchgear)$0.4B$1.0BNASA estimates ~240 kg of cable for 3 km at 2,800 V [src 15]; rest ESTIMATE; × $0.4–1.0M/kg
Integration, testing, operations$0.1B$0.3BESTIMATE

M05 · Site preparation, landing pads and roads · $2.88–7.3B

ItemLowHighBasis
Excavator robots ×4 (IPEx / RASSOR class)$0.1B$0.3BESTIMATE
Delivery of excavators (~1.2 t, medium landers)$0.48B$1.2B4 × ~300 kg scaled-up units (C05.1 ESTIMATE; RASSOR 2.0 is 65 kg dry, IPEx 30 kg-class [src 2]) × $0.4–1.0M/kg
Regolith sintering / construction robots ×2$0.2B$0.5BESTIMATE; ICON's NASA R&D contract alone is $57.2M [src 4]
Delivery of construction robots (~3 t)$1.2B$3.0B3 t × $0.4–1.0M/kg (ESTIMATE)
Binder / additives shipped from Earth (~2 t)$0.8B$2.0B2 t × $0.4–1.0M/kg (ESTIMATE); only if sintering alone is not enough
Engineering and operations$0.1B$0.3BESTIMATE

M06 · Oxygen and water pilot plants · $3.8–9.8B

ItemLowHighBasis
Pilot plant development (oxygen + water)$0.5B$1.5BESTIMATE; Blue Alchemist's 2023 NASA Tipping Point award was $34.7M for an earlier stage [src 11]
Delivery of oxygen plant (~3 t, medium lander)$1.2B$3.0B3 t × $0.4–1.0M/kg (mass ESTIMATE)
Delivery of water plant + PSR excavator (~3 t)$1.2B$3.0B3 t × $0.4–1.0M/kg (mass ESTIMATE)
Delivery of tanks, liquefier, electrolyser (~2 t)$0.8B$2.0B2 t × $0.4–1.0M/kg (mass ESTIMATE)
Operations and science, 3 years$0.1B$0.3BESTIMATE

M07 · Surface mobility · $1.2–3.3B

ItemLowHighBasis
LTV services (2 rovers)$0.45B$1.0BNASA's 2026 LTV task orders: $219M (Astrolab) + $220M (Lunar Outpost) [src 1]; high side adds services growth
Pressurised rover: partnership share$0.5B$1.5BESTIMATE; cost share in a JAXA-led programme
Utility robots, carts and spares, including delivery (~250 kg)$0.2B$0.6BESTIMATE; 250 kg × $0.6–1.2M/kg delivery plus hardware
Teleoperation centre and driver training$0.05B$0.2BESTIMATE

M08 · First habitat and crewed sorties · $10.6–30.2B

ItemLowHighBasis
Habitat module (build, test)$1.0B$3.0BESTIMATE
Habitat delivery (~15 t, heavy cargo lander)$3.0B$9.0B15 t [src 11] × $0.2–0.6M/kg (ESTIMATE)
4 crewed sorties (crew launch + landing)$6.0B$16.4BHigh: $4.1B per SLS/Orion launch (OIG) [src 6]; low assumes commercial crew transport at ~$1.5B per mission (ESTIMATE)
Spacesuits, EVA tools, airlock/dust lock$0.3B$0.8BESTIMATE
Mission operations and crew training$0.3B$1.0BESTIMATE

M09 · Permanent crew presence · $26.9–88.6B

ItemLowHighBasis
2 more habitat modules (build)$2.0B$6.0BESTIMATE; same class as M08
Delivery of 2 modules (~30 t, heavy cargo)$6.0B$18.0B30 t × $0.2–0.6M/kg (ESTIMATE)
Extra excavators for burial$0.2B$0.5BESTIMATE; reuses M05 fleet
Life support closure upgrades$0.3B$1.0BESTIMATE
8 crew rotations over 4 years$12.0B$32.8B8 × $1.5–4.1B per crewed mission (see M08)
Resupply, ~29–47 t over 4 years$5.8B$28.2B4 crew × 1,461 days × 5–8 kg per crew-day (ESTIMATE after loop closure) × $0.2–0.6M/kg
Medical and radiation monitoring$0.2B$0.5BESTIMATE
Surface and ground operations, 4 years$0.4B$1.6BESTIMATE

M10 · Growing food · $6.35–21.35B

ItemLowHighBasis
Greenhouse modules (build)$0.5B$1.5BESTIMATE
Delivery of greenhouse modules (~17–21 t, heavy cargo)$3.4B$12.6B17–21 t (C10.1 ESTIMATE) × $0.2–0.6M/kg
Extra ~60 kW for lighting: one more fission unit (build + ~10 t delivery)$2.25B$6.75BC10.1 sizing (~61 kW); build $0.25–0.75B ESTIMATE + 10 t × $0.2–0.6M/kg
Crop research and ground analog$0.2B$0.5BESTIMATE

M11 · Propellant and industrial-scale ISRU · $14.0–42.0B

ItemLowHighBasis
Plant modules ×10 (build)$1.0B$3.0BESTIMATE; repeat builds of M06 modules
Delivery of plant modules (~30 t)$6.0B$18.0B30 t × $0.2–0.6M/kg (ESTIMATE)
Two more fission units (build)$0.5B$1.5BESTIMATE; repeat builds
Delivery of fission units (~20 t)$4.0B$12.0B2 × ~10 t × $0.2–0.6M/kg
Cryogenic depot and transfer equipment (build + ~10 t delivery)$2.5B$7.5BESTIMATE

M12 · Manufacturing and construction from regolith · $5.5–16.0B

ItemLowHighBasis
Factory equipment development$1.0B$3.0BESTIMATE
Delivery of factory equipment (~20 t)$4.0B$12.0B20 t × $0.2–0.6M/kg (ESTIMATE)
Operations$0.5B$1.0BESTIMATE

M13 · Self-sustaining colony · $40.0–120.0B

ItemLowHighBasis
Operations, 10 years$30.0B$80.0BESTIMATE; ISS operations cost about $3B per year [benchmark]; range $3–8B/yr
Expansion: habitats, power, greenhouses$10.0B$40.0BESTIMATE; mostly built from local materials by this stage
ProjectOPEN MOON · Self-sustaining lunar colony
DocumentOM-200
Revision1.2 · Draft