Costs
Programme total: $122B to $367B ESTIMATE, in today's US dollars, spread across the milestone windows. Costs are built bottom-up from published contract values and programme costs wherever they exist, and from delivered-mass × price-per-kg where they don't. Each milestone page shows the line items and the basis for every one.
These are planning estimates, not quotes. Space programmes routinely overrun; NASA's own OIG has documented large overruns on SLS, Orion and OSAM-1. The high column includes margin for that, but real costs could still be higher. Where a figure is a contract ceiling, the actual spend may be lower.
Delivery pricing used throughout the plan: small landers (under 1 t) at up to $1.2M per kg landed, Astrobotic's published price [benchmark]. Medium (about 3 t, Blue Moon Mark 1 class) and large (about 15 t) landers have no published price, so the plan assumes $0.4M–$1.0M per kg for medium and $0.2M–$0.6M per kg for large (ESTIMATE) and shows this assumption on every line that uses it. If heavy-cargo prices fall as SpaceX and Blue Origin claim, the totals drop sharply; if not, they rise.
Benchmarks we price against
| Benchmark | Figure | Source |
|---|---|---|
| ISS design, development and build | More than $100B | NASA, Ignition release (Mar 2026) |
| ISS operating cost | About $3B per year | NASA OIG IG-22-005 (Nov 2021) |
| ISS commercial resupply, CRS-1 | $191.3M per flight, about $63,200 per kg of upmass | NASA OIG IG-18-016 (Apr 2018) |
| ISS commercial resupply, CRS-2 (projected) | $300.6M per flight, about $71,800 per kg | NASA OIG IG-18-016 (Apr 2018) |
| Artemis spending FY2012–FY2025 (projection) | $93B; $4.1B per SLS/Orion launch | NASA OIG IG-22-003 (Nov 2021) |
| NASA total budget FY2026 (regular appropriation) | $24.438B, of which Exploration $7.783B | CRS R43419 (Jun 2026) |
| Lunar Terrain Vehicle task orders (2026) | Astrolab $219M, Lunar Outpost $220M | NASA RELEASE26-046 (May 2026) |
| Rover delivery to the south pole (Blue Origin) | $188M plus $280.4M option, for two rovers in 2028 | NASA RELEASE26-046 (May 2026) |
| VIPER delivery (CLPS CS-7, Blue Origin) | Up to $190M | NASA release (Sep 2025) |
| Lunar relay services (Intuitive Machines) | Up to $4.82B maximum contract value | NASA release (Sep 2024) |
| ESA Moonlight phase 1 (Telespazio) | €123M | European Spaceflight (Mar 2025), reporting the Oct 2024 ESA contract |
| ICON Project Olympus construction R&D | $57.2M SBIR Phase III | ICON (Nov 2022) |
| Blue Alchemist (oxygen and solar cells from regolith) | $34.7M NASA Tipping Point | NASA, 2023 Tipping Point selections (Jul 2023) |
| Published price to the lunar surface (Astrobotic) | $1.2M per kg to the surface; $300k per kg to lunar orbit | Astrobotic Payload User's Guide v5.0 (Aug 2021) |
| CLPS delivery task orders, cost growth | Eight orders grew from $781.4M to $984.3M (+26%); average delay 14 months | NASA OIG IG-24-013 (Jun 2024) |
| Human Landing System programme | $6.9B obligated since 2019; $18.3B estimated through FY2030 | NASA OIG IG-26-004 (Mar 2026) |
| Large cargo lander class | About 15 t (33,000 lb) per cargo landing | NASA HLS IAC 2026 presentation (Oct 2026) |
| NASA Moon Base (reported) | About $20B over 7 years; $6B for expanded CLPS over a decade | Planetary Society, citing NASA documents (2026) |
| CLPS 2 contract vehicle | 10-year IDIQ, $10B combined ceiling, 8 companies | NASA (Nov 2026) |
| Vertical Solar Array Technology prototypes | $19.4M total across three companies (2022) | NASA RELEASE 22-090 (Aug 2022) |
| Falcon Heavy list price | $97M (raised from $90M in Mar 2022) | Space.com (Mar 2022) |
By milestone
M00 · Programme set-up and site selection · $0.05–0.15B
| Item | Low | High | Basis |
|---|---|---|---|
| Core engineering team, 2 years | $0.04B | $0.11B | ESTIMATE: 60–150 full-time staff at ~$350k loaded cost per year |
| Computing, data processing, illumination modelling | $0.005B | $0.02B | ESTIMATE |
| Legal, international coordination | $0.005B | $0.02B | ESTIMATE |
M01 · Robotic prospecting and ground truth · $0.5–1.2B
| Item | Low | High | Basis |
|---|---|---|---|
| Prospecting rover ×2 (design, build, test) | $0.2B | $0.5B | ESTIMATE. Smaller than LTV-class rovers, whose task orders are $219–220M each [benchmark] |
| Delivery to the south pole ×2 | $0.25B | $0.5B | VIPER delivery task order up to $190M each (CS-7); range covers price growth |
| Operations, science team, data release | $0.05B | $0.2B | ESTIMATE |
M02 · Transport to the surface · $0.95–2.2B
| Item | Low | High | Basis |
|---|---|---|---|
| Common payload interface and integration team (5 years) | $0.15B | $0.4B | ESTIMATE |
| Surface offloading crane ×2 (LSMS-class) | $0.1B | $0.3B | NASA proposed a $22M Phase I to reach a TRL 6 proto-flight LSMS [src 7]; flight units and delivery added (ESTIMATE) |
| Delivery of 2 cranes (~1 t total) on small/medium landers | $0.6B | $1.2B | 1 t × $0.6–1.2M/kg (ESTIMATE; $1.2M/kg is Astrobotic's published price) |
| Schedule and cost-growth reserve (30%) | $0.1B | $0.3B | Total value of NASA's first eight CLPS task orders grew nearly 26% [src 9] |
M03 · Communications, navigation and time · $0.72–1.94B
| Item | Low | High | Basis |
|---|---|---|---|
| Relay and ground-station service fees, 5 years | $0.15B | $0.5B | ESTIMATE. NASA's relay contract has a maximum potential value of $4.82B [src 1] |
| Backup relay smallsat ×1 (build + launch to lunar orbit) | $0.15B | $0.4B | ESTIMATE; ~300 kg at $300k/kg to lunar orbit ≈ $90M delivery [src 8] plus spacecraft |
| Surface LTE base station, mesh radios, rim relay masts | $0.05B | $0.15B | ESTIMATE hardware |
| Delivery of base comms node and rim relay masts (~400 kg) | $0.24B | $0.48B | ~220 kg comms node (C03.1) + rim masts (C03.2), ESTIMATE × $0.6–1.2M/kg ($1.2M/kg published [src 8]) |
| Optical terminal for the base (high-rate Earth link) | $0.08B | $0.25B | ESTIMATE; based on O2O/LCRD class terminals |
| Operations and network engineering, 5 years | $0.05B | $0.16B | ESTIMATE |
M04 · Surface power grid · $8.6–22.5B
| Item | Low | High | Basis |
|---|---|---|---|
| 2 × 10 kW vertical solar arrays (hardware) | $0.05B | $0.15B | ESTIMATE; NASA's three VSAT prototypes cost $19.4M in total [src 4] |
| Delivery of 10 kW arrays (~2 t, small landers) | $1.2B | $2.4B | 2 t × $0.6–1.2M/kg (mass ESTIMATE) |
| 2 × 50 kW VSAT-XL towers (hardware) | $0.1B | $0.3B | ESTIMATE |
| Delivery of VSAT-XL (~6 t, medium landers) | $2.4B | $6.0B | 6 t × $0.4–1.0M/kg (mass ESTIMATE) |
| 40 kWe fission unit (develop, build, qualify) | $1.0B | $3.0B | ESTIMATE; Congress gave $250M for Fission Surface Power in FY2026 alone [src 16] |
| Delivery of fission unit (~10 t, heavy lander) | $2.0B | $6.0B | NASA reference design ~10 t for 40 kWe [src 1] × $0.2–0.6M/kg |
| Regenerative fuel cell storage, ~3 MWh (hardware) | $0.05B | $0.15B | ESTIMATE |
| Delivery of storage (~3 t, medium lander) | $1.2B | $3.0B | 3 MWh ÷ ~500 Wh/kg ≈ 6 t at cell level; ~3 t assumes partial reuse of ISRU tanks (ESTIMATE) × $0.4–1.0M/kg |
| Cables, converters, switchgear (hardware) | $0.05B | $0.15B | ESTIMATE |
| Delivery of grid hardware (~1 t: ~5 km of cable, converters, switchgear) | $0.4B | $1.0B | NASA estimates ~240 kg of cable for 3 km at 2,800 V [src 15]; rest ESTIMATE; × $0.4–1.0M/kg |
| Integration, testing, operations | $0.1B | $0.3B | ESTIMATE |
M05 · Site preparation, landing pads and roads · $2.88–7.3B
| Item | Low | High | Basis |
|---|---|---|---|
| Excavator robots ×4 (IPEx / RASSOR class) | $0.1B | $0.3B | ESTIMATE |
| Delivery of excavators (~1.2 t, medium landers) | $0.48B | $1.2B | 4 × ~300 kg scaled-up units (C05.1 ESTIMATE; RASSOR 2.0 is 65 kg dry, IPEx 30 kg-class [src 2]) × $0.4–1.0M/kg |
| Regolith sintering / construction robots ×2 | $0.2B | $0.5B | ESTIMATE; ICON's NASA R&D contract alone is $57.2M [src 4] |
| Delivery of construction robots (~3 t) | $1.2B | $3.0B | 3 t × $0.4–1.0M/kg (ESTIMATE) |
| Binder / additives shipped from Earth (~2 t) | $0.8B | $2.0B | 2 t × $0.4–1.0M/kg (ESTIMATE); only if sintering alone is not enough |
| Engineering and operations | $0.1B | $0.3B | ESTIMATE |
M06 · Oxygen and water pilot plants · $3.8–9.8B
| Item | Low | High | Basis |
|---|---|---|---|
| Pilot plant development (oxygen + water) | $0.5B | $1.5B | ESTIMATE; Blue Alchemist's 2023 NASA Tipping Point award was $34.7M for an earlier stage [src 11] |
| Delivery of oxygen plant (~3 t, medium lander) | $1.2B | $3.0B | 3 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Delivery of water plant + PSR excavator (~3 t) | $1.2B | $3.0B | 3 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Delivery of tanks, liquefier, electrolyser (~2 t) | $0.8B | $2.0B | 2 t × $0.4–1.0M/kg (mass ESTIMATE) |
| Operations and science, 3 years | $0.1B | $0.3B | ESTIMATE |
M07 · Surface mobility · $1.2–3.3B
| Item | Low | High | Basis |
|---|---|---|---|
| LTV services (2 rovers) | $0.45B | $1.0B | NASA's 2026 LTV task orders: $219M (Astrolab) + $220M (Lunar Outpost) [src 1]; high side adds services growth |
| Pressurised rover: partnership share | $0.5B | $1.5B | ESTIMATE; cost share in a JAXA-led programme |
| Utility robots, carts and spares, including delivery (~250 kg) | $0.2B | $0.6B | ESTIMATE; 250 kg × $0.6–1.2M/kg delivery plus hardware |
| Teleoperation centre and driver training | $0.05B | $0.2B | ESTIMATE |
M08 · First habitat and crewed sorties · $10.6–30.2B
| Item | Low | High | Basis |
|---|---|---|---|
| Habitat module (build, test) | $1.0B | $3.0B | ESTIMATE |
| Habitat delivery (~15 t, heavy cargo lander) | $3.0B | $9.0B | 15 t [src 11] × $0.2–0.6M/kg (ESTIMATE) |
| 4 crewed sorties (crew launch + landing) | $6.0B | $16.4B | High: $4.1B per SLS/Orion launch (OIG) [src 6]; low assumes commercial crew transport at ~$1.5B per mission (ESTIMATE) |
| Spacesuits, EVA tools, airlock/dust lock | $0.3B | $0.8B | ESTIMATE |
| Mission operations and crew training | $0.3B | $1.0B | ESTIMATE |
M09 · Permanent crew presence · $26.9–88.6B
| Item | Low | High | Basis |
|---|---|---|---|
| 2 more habitat modules (build) | $2.0B | $6.0B | ESTIMATE; same class as M08 |
| Delivery of 2 modules (~30 t, heavy cargo) | $6.0B | $18.0B | 30 t × $0.2–0.6M/kg (ESTIMATE) |
| Extra excavators for burial | $0.2B | $0.5B | ESTIMATE; reuses M05 fleet |
| Life support closure upgrades | $0.3B | $1.0B | ESTIMATE |
| 8 crew rotations over 4 years | $12.0B | $32.8B | 8 × $1.5–4.1B per crewed mission (see M08) |
| Resupply, ~29–47 t over 4 years | $5.8B | $28.2B | 4 crew × 1,461 days × 5–8 kg per crew-day (ESTIMATE after loop closure) × $0.2–0.6M/kg |
| Medical and radiation monitoring | $0.2B | $0.5B | ESTIMATE |
| Surface and ground operations, 4 years | $0.4B | $1.6B | ESTIMATE |
M10 · Growing food · $6.35–21.35B
| Item | Low | High | Basis |
|---|---|---|---|
| Greenhouse modules (build) | $0.5B | $1.5B | ESTIMATE |
| Delivery of greenhouse modules (~17–21 t, heavy cargo) | $3.4B | $12.6B | 17–21 t (C10.1 ESTIMATE) × $0.2–0.6M/kg |
| Extra ~60 kW for lighting: one more fission unit (build + ~10 t delivery) | $2.25B | $6.75B | C10.1 sizing (~61 kW); build $0.25–0.75B ESTIMATE + 10 t × $0.2–0.6M/kg |
| Crop research and ground analog | $0.2B | $0.5B | ESTIMATE |
M11 · Propellant and industrial-scale ISRU · $14.0–42.0B
| Item | Low | High | Basis |
|---|---|---|---|
| Plant modules ×10 (build) | $1.0B | $3.0B | ESTIMATE; repeat builds of M06 modules |
| Delivery of plant modules (~30 t) | $6.0B | $18.0B | 30 t × $0.2–0.6M/kg (ESTIMATE) |
| Two more fission units (build) | $0.5B | $1.5B | ESTIMATE; repeat builds |
| Delivery of fission units (~20 t) | $4.0B | $12.0B | 2 × ~10 t × $0.2–0.6M/kg |
| Cryogenic depot and transfer equipment (build + ~10 t delivery) | $2.5B | $7.5B | ESTIMATE |
M12 · Manufacturing and construction from regolith · $5.5–16.0B
| Item | Low | High | Basis |
|---|---|---|---|
| Factory equipment development | $1.0B | $3.0B | ESTIMATE |
| Delivery of factory equipment (~20 t) | $4.0B | $12.0B | 20 t × $0.2–0.6M/kg (ESTIMATE) |
| Operations | $0.5B | $1.0B | ESTIMATE |
M13 · Self-sustaining colony · $40.0–120.0B
| Item | Low | High | Basis |
|---|---|---|---|
| Operations, 10 years | $30.0B | $80.0B | ESTIMATE; ISS operations cost about $3B per year [benchmark]; range $3–8B/yr |
| Expansion: habitats, power, greenhouses | $10.0B | $40.0B | ESTIMATE; mostly built from local materials by this stage |