Plan / Phase 1 / M05
M05 · Phase 1 · 2028–2032

Site preparation, landing pads and roads

Robots build hardened landing pads, roads and protective berms so landers stop sandblasting the base and rovers can drive safely between sites.
Objective

Build at least two hardened landing pads that stop rocket exhaust from blasting regolith across the base, graded roads linking pads, power towers, the reactor, the ISRU plant and the habitat zone, and berms that shield key equipment from ejecta and radiation.

Exit criteria · what "done" means
#Criterion
EC-1At least two hardened pads survive repeated landings with no measurable damage to equipment beyond 500 m.
EC-2Graded roads connect every fixed site; rovers drive them autonomously.
EC-3Ejecta berms around each pad and a shielding berm at the reactor.
EC-4Measured ejecta during a landing on a hardened pad confirms the model used for the keep-out zones.
Workstreams · 5
1

Excavation

Dig, move and level regolith.

  • IPEx-class excavators (bucket drums)
  • Grading and compaction
  • Stockpiles for ISRU and berms
2

Landing pads

A hard surface that does not erode under a rocket plume.

  • Laser or microwave sintered regolith
  • Interlocking sintered pavers
  • Regolith-polymer pad as fallback
3

Roads

Smooth, mapped routes between sites.

  • Graded and compacted regolith
  • Sintered surface on busy sections
  • Marker beacons for navigation
4

Berms

Walls of piled regolith.

  • Ejecta berms around pads
  • Reactor shield berm
  • Later: habitat burial (M09)
5

Dust control

Keep dust off everything that matters.

  • Pads 1+ km from solar towers
  • Sintered work areas
  • Dust-tolerant seals and connectors
Technology · what we use and how ready it is
TechnologyUsed forStatus todayTRL
NASA ISRU Pilot Excavator (IPEx)1Excavation and gradingTRL 5 design (2024); target 42 kg/h, 10 t over an 11-day mission; no flight date 5
RASSOR 2.03Light excavationUnder 100 kg; nominal mission concept of 35 loads of 20 kg per 24 h, about 700 kg/day 5
ICON Project Olympus (laser vitreous transformation)4Pads, roads and structures from regolith$57.2M NASA SBIR Phase III contract (2022) for landing pads, blast shields and roads 4 develop
Sintered basalt pavers / regolith-polymer pads5Landing padsHot-fire tested on the ground by NASA KSC 4 develop
Components · detailed breakdowns
Plan of action

Why pads come before habitats

When a lander touches down on bare regolith, its exhaust throws dust and rocks outward at high speed. In 1969 Apollo 12 landed 155 m from the Surveyor III probe, and its plume reached the probe. NASA modelling of that landing gives fine dust (under 13 µm) reaching Surveyor at up to 130 m/s7. Larger engines on heavier landers will throw more material further. A base that expects regular cargo and crew landings has to stop this, or every landing damages the solar arrays, radiators and habitats already there.

What exists today

  • Excavation. NASA has largely built a TRL-5 version of IPEx, a 30 kg-class excavator (90% fabricated by June 2024). It’s designed to dig 10 t of regolith at 42 kg/h over an 11-day mission12. Its predecessor, RASSOR 2.0, is larger, at 65 kg dry2. NASA’s RASSOR concept has it making 35 trips with 20 kg loads every 24 hours, about 700 kg a day3. These are design figures, not lunar measurements.
  • Construction. ICON holds a $57.2M NASA SBIR Phase III contract, building on its Project Olympus, to develop a system for building landing pads, blast shields and roads from lunar materials4. NASA describes ICON’s process as using high-powered lasers to melt regolith. Its Duneflow experiment flew on a Blue Origin suborbital rocket in February 20258.
  • Pad tests. NASA has hot-fire tested sintered basalt pavers and regolith-polymer pads against rocket engines on the ground56.

Step-by-step

  1. Survey. Use M01 geotechnical data and the M00 hazard maps to set pad and road locations.
  2. Land the excavators on a small lander, on the pad site itself.
  3. Grade and compact the first pad area and the roads to the power towers.
  4. Sinter pad 1 in stages, then test it with a small lander. Measure ejecta with cameras and witness plates.
  5. Scale up: a larger pad 2 for medium and heavy landers, plus berms.
  6. Build roads and stockpiles. Pile excavated regolith for the M06 ISRU feedstock and for the M09 habitat burial.

Dust is a design requirement, not an afterthought

NASA’s review of Apollo found that lunar dust abraded, clogged and coated equipment and caused seal failures. On Apollo 12, all the environmental and gas sample seals failed because of dust9. Every Open Moon mechanism has to:

  • tolerate dust
  • be covered when idle
  • work on sintered ground wherever possible
Cost build-up
ItemLowHighBasis
Excavator robots ×4 (IPEx / RASSOR class)$0.1B$0.3BESTIMATE
Delivery of excavators (~1.2 t, medium landers)$0.48B$1.2B4 × ~300 kg scaled-up units (C05.1 ESTIMATE; RASSOR 2.0 is 65 kg dry, IPEx 30 kg-class [src 2]) × $0.4–1.0M/kg
Regolith sintering / construction robots ×2$0.2B$0.5BESTIMATE; ICON's NASA R&D contract alone is $57.2M [src 4]
Delivery of construction robots (~3 t)$1.2B$3.0B3 t × $0.4–1.0M/kg (ESTIMATE)
Binder / additives shipped from Earth (~2 t)$0.8B$2.0B2 t × $0.4–1.0M/kg (ESTIMATE); only if sintering alone is not enough
Engineering and operations$0.1B$0.3BESTIMATE
Total$2.88B$7.3BESTIMATE robot fleet plus delivery; pad material is mostly local regolith

Mission profile

Window2028–2032
Phase1
Depends onM01, M02, M04
Pads2 hardened pads (small/medium landers first, then heavy)
Roads~5 km graded and compacted
BermsEjecta berms around pads; shielding berm for the reactor
Fleet4 excavators + 2 sintering/construction robots
Cost$2.88–7.3B EST.
Lowest critical TRL · 5 / 9

Failure modes · 5

FM-1 · Critical
Rocket exhaust blasts dust and rock across the site; Apollo 12 landed 155 m from Surveyor III and its plume reached it
Fix: Hardened pads before heavy landers; berms; keep solar towers, reactor and habitat well away from pads
FM-2 · High
Sintering a pad that survives a large methane/oxygen engine has not been demonstrated on the Moon
Fix: Test small pads with small landers first; regolith-polymer pad as fallback; scale up step by step
FM-3 · High
Dust damages seals and mechanisms; on Apollo 12 all the environmental and gas sample seals failed
Fix: Dust-tolerant designs, covers, and sintered surfaces around work sites
FM-4 · Medium
Excavation rates on the Moon are unproven (IPEx targets are design goals, not measured)
Fix: Bring more excavators than needed; measure real rates in the first month and replan
FM-5 · Medium
Regolith properties at the site differ from simulants
Fix: Use M01 geotechnical data; adjust sintering settings on site

Sources

  1. NASA NTRS: IPEx TRL 5 design overview (ASCEND 2024) (2024)
  2. NASA NTRS: ISRU Pilot Excavator design and scaling (2022)
  3. NASA NTRS 20150022134: RASSOR 2.0 (2015)
  4. ICON: ICON to develop lunar surface construction system with $57.2M NASA award (Nov 2022)
  5. NASA: NASA tests landing pad materials for future lunar missions ()
  6. NASA NTRS: In-situ lunar launch and landing pad construction with regolith and thermoset polymers (2022)
  7. NASA NTRS 20120000029: Lunar plume ejecta (Apollo 12 / Surveyor III) (2012)
  8. NASA: NASA enables construction technology for Moon and Mars exploration (Olympus, Duneflow) (2025)
  9. Gaier, NASA/TM-2005-213610: The effects of lunar dust on EVA systems during Apollo (2005)
  10. NASA: Break the Ice Lunar Challenge winners (Jun 2024)