C05.3 · Component of M05

Regolith sintering and construction robot

A mobile robot that spreads thin layers of regolith and fuses them with a laser or microwave beam, building pad surfaces, road sections and berm crests from local material.
Sub-components · 5
1

Energy source

A high-power laser (baseline) or microwave applicator heats each layer to sinter and melt it onto the layer below.

  • Fibre laser modules (or magnetron and horn)
  • Beam delivery optics
  • Cooling loop and radiator
  • Dust-protected output window
BASIS: ICON laser VMX toolhead; NASA MSFC microwave tests · TRL 4
2

Gantry or arm

A robotic arm on a mobile base moves the toolhead across the work area in set paths.

  • 6-DOF thermal-vacuum rated arm
  • Mobile base with wheels
  • Stabiliser feet
  • Multi-tool end effector
BASIS: ICON TVAC robot arm · TRL 4
3

Feed system

Scoops, filters and tamps regolith into a flat, even layer before fusing.

  • Scoop and hopper
  • Sieve to remove large grains and rocks
  • Spreader blade
  • Tamp or roller
  • Interface to excavator dumps (C05.1)
BASIS: ICON scoop/tamp/filter system, designed with NASA KSC · TRL 4
4

Sensors

Sensors map the layer before fusing, watch temperature during fusing and check the result after.

  • Lidar or structured light for layer height
  • Thermal camera or microwave radiometer
  • Off-gas mass spectrometer
  • Visual cameras with dust covers
BASIS: MMPACT forward work list · TRL 3
5

Power and thermal

A tethered cable brings grid power; waste heat goes to a radiator.

  • Tether reel and connector
  • Power conversion for laser drivers
  • Battery for moves and safe shutdown
  • Radiator and heaters
BASIS: Plan design choice; M04 grid · TRL 4
Engineering notes

What it does

The construction robot turns loose regolith into a hard, ceramic-like surface. It builds the fused cores of the C05.2 landing pads, busy road sections and the crests of berms. It uses only local regolith, so Open Moon does not have to ship binder from Earth.

How it works

Energy source. ICON’s Laser Vitreous Multi-material Transformation (VMX) is a powder-bed method. The robot lays thin layers of regolith and fuses them with a laser. Each spot is preheated, sintered, melted onto the layer below and then crystallised2. ICON holds a $57.2M NASA SBIR Phase III contract for Project Olympus. Its stated targets are landing pads, blast shields and roads1. The other option is microwave sintering. NASA’s MMPACT project worked on it for pads and roads, aiming at a 2 t microwave paver vehicle4. Open Moon uses laser as the baseline and keeps microwave as an alternative.

Arm. ICON’s process uses a 6-DOF robot arm with a multi-tool end effector. ICON reported the arm working in thermal vacuum at subsystem scale. A full-scale test at NASA Marshall was planned for early 20242. Open Moon mounts the arm on a wheeled base.

Feed. ICON’s scoop, tamp and filter system was designed with NASA KSC2. C05.1 excavators dump regolith next to the robot. The robot sieves it, spreads it and tamps it flat.

Sensors. MMPACT lists the sensors still to be adapted: terrain mapping, applicator positioning, temperature measurement by radiometer or thermography, and off-gas mass spectrometry4.

Product. ICON’s vacuum-made VMX material measured about 50,000 psi compressive strength at 25 °C. After one year of lunar thermal-vacuum cycling it measured about 36,500 psi. Its density is 2.7 g/cm³2. ICON’s Duneflow experiment flew on a Blue Origin suborbital flight in February 2025. It tested regolith flow in about two minutes of lunar gravity3.

Sizing

The energy needed per kilogram of fused regolith is not published for VMX or MMPACT. The figure below is an assumption that contributors should replace with test data.

Item Value Basis
Beam power per unit 30 kW Design choice (ESTIMATE)
Energy to fuse 1 kg 1.5 MJ ASSUMPTION, unsourced
Rate per unit 72 kg/h 30 kW × 3,600 s ÷ 1.5 MJ
Rate, 2 units 144 kg/h 2 × 72
Pad 1 core (~95 t, C05.2) ~660 h, ~28 days nonstop 95,000 ÷ 144
Pad 2 core (~265 t, C05.2) ~1,840 h, ~77 days nonstop 265,000 ÷ 144
Grid draw, 2 units ~70 kW 60 kW beam + ~10 kW other loads (ESTIMATE)

At 50% uptime, pad 1 takes about 2 months and pad 2 about 5 months. That is a large share of the early grid. So fusing should be scheduled when the ISRU plant is not running at full power.

Testing and qualification

  1. Coupons in vacuum from site-like simulants. Measure strength, density and energy per kilogram.
  2. Hot-fire tests of fused coupons, as NASA did for pavers and polymer pads5.
  3. Full-scale arm and toolhead in a thermal vacuum chamber, building a multi-square-metre section.
  4. Field test on Earth: build a 10 m test pad with the excavators, in the open.
  5. On the Moon: fuse a small test patch, scan it and test it. Then build pad 1.

Open questions

  • What is the real energy per kilogram in vacuum, with site regolith?
  • Laser or microwave: which tolerates dust, volatiles and varying minerals better?
  • How long do optics or applicators last before replacement?
  • Can the same robot build vertical structures for M09 later?
Problems and solutions · 7
SeverityProblemSolution
CriticalLaser or microwave fusing at pad scale has not been shown in vacuum; ICON's arm was only scheduled for full-scale TVAC testing in 2024Build a full-size pad section in a large vacuum chamber before flight; keep paver and polymer fallbacks.
HighFusing rate and energy per kilogram are not published, so build times are uncertainMeasure rate and energy in chamber tests; size the fleet and grid power from measured data.
HighRegolith is a strong insulator and its microwave absorption varies with mineralogyTune settings to M01 site samples; carry both laser and microwave options until tests pick one.
HighOptics and applicators face an 1100 °C surface and released volatilesPurge or shutter the output window; plan window and applicator replacement as spares.
MediumDust during site prep can cause navigation and positioning errorsUse fixed survey markers; fuse areas soon after they are prepared.
MediumUneven layers give weak spots and varying densityScan each layer before fusing; re-tamp or skip areas out of tolerance; inspect finished areas.
MediumHigh-power laser is an eye and equipment hazard near crewRobot works only when no crew are in line of sight; interlocks and keep-out zones.

Specification

HeritageICON Project Olympus (laser VMX); NASA MMPACT microwave sintering
Quantity2 units (M05 plan)
Mass per unit~1.5 t (ESTIMATE; M05 budgets ~3 t for two; NASA studied a 2 t microwave paver vehicle)
Beam power30 kW per unit (design choice, ESTIMATE)
Fusing rate~72 kg/h per unit (ESTIMATE, see Sizing)
LayerThin layers built up to 50 mm surfaces (design choice)
ProductFused regolith, ~2.7 g/cm³, ~50,000 psi compressive (ICON lab data)
PowerCable from the M04 grid, with a small battery for moves
ControlAutonomous build paths, supervised from Earth
Technology readiness · TRL 4 / 9

Sources

  1. ICON: ICON to develop lunar surface construction system with $57.2M NASA award (Nov 2022)
  2. ICON: Project Olympus, LSIC slides (Jan 2024)
  3. NASA: NASA enables construction technology for Moon and Mars exploration (Olympus, Duneflow) (May 2025)
  4. Effinger, NASA MSFC: Microwave sintering lunar landing pads and horizontal infrastructure (MMPACT) (Dec 2020)
  5. Gelino et al., NASA KSC: In-situ lunar launch and landing pad construction with regolith-thermoset polymer composites (2022)