Plan / Phase 2 / M08
M08 · Phase 2 · 2031–2035

First habitat and crewed sorties

Land the first surface habitat and fly crews for stays of two to four weeks, leaving more infrastructure behind on every visit.
Objective

Land a habitat for two to four crew, fly four crewed sorties of 14–30 days, and use them to commission the power, ISRU and mobility systems with people on site.

Exit criteria · what "done" means
#Criterion
EC-1Habitat landed, deployed and powered from the M04 grid, with life support running uncrewed for at least 3 months before the first crew.
EC-2Four sorties of 14–30 days flown with no serious injury.
EC-3Each crew completes a planned list of maintenance, installation and science tasks.
EC-4Dust kept out of the habitat to a measured standard.
Workstreams · 6
1

Habitat

A rigid, wheeled module that can be moved and later buried.

  • ~15 t class pressurised module
  • Delivered on a heavy cargo lander
  • Moved by LTVs to the habitat zone
2

Life support (open loop + recycling)

ISS-derived systems.

  • Water recovery
  • Oxygen generation
  • CO₂ removal
  • Top-up from M06 water and oxygen
3

Dust control

Keep dust out of the cabin.

  • Dust lock / suitport
  • Brushes and electrostatic cleaning
  • Sintered ground around the hatch
4

EVA

Working outside.

  • AxEMU-class suits
  • Tools for maintenance
  • LTV range limits for walk-back safety
5

Crew transport

Seats to and from the surface.

  • NASA Artemis / Moon Base partnership
  • Commercial landers when certified
6

Medical

Treat what can be treated, evacuate what can't.

  • Medical kit and ultrasound
  • Telemedicine with 5–12 s delay
  • Evacuation plan
Technology · what we use and how ready it is
TechnologyUsed forStatus todayTRL
Thales Alenia Space Multi-Purpose Habitation (MPH)11Surface habitatPreliminary design contract with ASI (Jul 2025); ~15 t, ~3 m × 6 m, 10-yr life; launch planned 2033 5
Sierra Space LIFE inflatable2Alternative expandable habitatFull-scale burst test reached 77 psi before bursting (reported Jan 2024), 27% above NASA's recommended 60.8 psi 5
ISS life support (ECLSS)3Air and water recyclingFlight-proven; 98% water recovery demonstrated 2023 9
Axiom AxEMU spacesuit4MoonwalksCritical design review closed 13 Nov 2026; qualification next 6
Heavy cargo lander (Starship / Blue Moon Mk2 cargo)5Habitat delivery~15 t class; habitat delivery NET FY2033 per NASA 6
Components · detailed breakdowns
Plan of action

The habitat

  • Thales Alenia Space MPH. Thales is designing it for the Italian Space Agency: about 3 m × 6 m, about 15 t, on wheels, with a minimum 10-year life. Launch is planned for 2033111.
  • Inflatable alternative. Sierra Space’s LIFE module held 77 psi before bursting in a full-scale test, 27% above NASA’s recommended level2.

Open Moon designs its habitat zone for a rigid ~15 t module first, with room for inflatable modules later. Press reports describe the MPH as sized for two astronauts on one 7–30-day mission a year11, so early sorties put two people on the surface. Four-person stays wait for a second module or the docked pressurised rover (M07). NASA expects habitats to arrive on cargo landers no earlier than FY20335.

Life support

  • Base system. The habitat uses ISS-derived life support. The ISS demonstrated 98% water recovery in 20233, although NASA’s reference page still describes routine recovery as about 90%9.
  • Local top-up. During sorties the system is topped up with water and oxygen from the M06 pilot plants. This is the first time the crew depends on lunar resources.

Why crew transport dominates the cost

  • Upper bound. NASA’s Inspector General put each SLS/Orion launch at about $4.1B6. That figure doesn’t include the lander.
  • Lower bound. This plan assumes commercial crew transport eventually costs about $1.5B per mission, but that is an estimate, not a published price.
  • Why it matters. The uncertainty in crew transport is the biggest single uncertainty in the whole budget.

Step-by-step

  1. Land the habitat on a heavy lander at pad 2 (M05).
  2. Move it into place. LTVs tow it to the habitat zone, where it’s connected to the habitat microgrid (M04).
  3. Run uncrewed for 3 months. Life support, leak checks and dust lock tests run from Earth.
  4. Sortie 1 (14 days). Commission the habitat; inspect power and ISRU; first moonwalks.
  5. Sorties 2–4 (up to 30 days). Maintenance, installation of M09 equipment, and medical research on partial gravity.
  6. Leave equipment behind. Each crew leaves the habitat ready for the next one.
Cost build-up
ItemLowHighBasis
Habitat module (build, test)$1.0B$3.0BESTIMATE
Habitat delivery (~15 t, heavy cargo lander)$3.0B$9.0B15 t [src 11] × $0.2–0.6M/kg (ESTIMATE)
4 crewed sorties (crew launch + landing)$6.0B$16.4BHigh: $4.1B per SLS/Orion launch (OIG) [src 6]; low assumes commercial crew transport at ~$1.5B per mission (ESTIMATE)
Spacesuits, EVA tools, airlock/dust lock$0.3B$0.8BESTIMATE
Mission operations and crew training$0.3B$1.0BESTIMATE
Total$10.6B$30.2BESTIMATE crew transport dominates

Mission profile

Window2031–2035
Phase2
Depends onM02, M03, M04, M05, M07
Habitat1 rigid module, ~15 t class (e.g. Thales Alenia MPH: ~3 m × 6 m, 10-year life)
Crew2 per sortie at first (MPH is reported as a 2-crew module), 4 once a second module or the pressurised rover is docked
Stays14–30 days
Sorties4
SuitsAxiom AxEMU class
Cost$10.6–30.2B EST.
Lowest critical TRL · 5 / 9

Failure modes · 6

FM-1 · Critical
Crew landing systems are not yet certified; first crewed landing is planned for 2028
Fix: Fly sorties only after the lander has a demonstrated crewed landing; partner with NASA Moon Base schedule
FM-2 · High
Dust in the cabin (on Apollo, dust degraded suit seals and every sample-container seal failed)
Fix: Dust lock or suitports; strict cleaning; sintered surfaces at the hatch
FM-3 · High
Spacesuit schedule risk (OIG warned demonstrations could slip to 2031)
Fix: Keep sortie dates flexible; early sorties with minimal EVA
FM-4 · High
Medical emergency far from a hospital, with 5–12 s operational delays
Fix: Trained crew medic, telemedicine, and an evacuation plan with a lander on standby
FM-5 · High
The MPH is reported as sized for 2 crew on one 7–30-day mission a year, while crewed landers carry 4
Fix: Fly 2-crew surface teams first; add fold-down sleep stations; reach 4 crew by docking the pressurised rover or a second module (M09)
FM-6 · Medium
Habitat sits on the surface unshielded during sorties
Fix: Short stays; storm shelter area with water walls; burial in M09

Sources

  1. Thales Alenia Space: contract with ASI to develop lunar Multi-Purpose Habitation module (Jul 2025)
  2. TechCrunch: Sierra Space's inflatable habitat blows up as planned (Jan 2024)
  3. Space.com: ISS hits 98% water recycling milestone (Jun 2023)
  4. Axiom Space: completes NASA's critical design review for next-generation spacesuit (Nov 2026)
  5. NASA HLS IAC 2026 presentation (cargo landers, habitat delivery NET FY2033) (Oct 2026)
  6. NASA OIG IG-22-003: NASA's management of the Artemis missions ($4.1B per launch) (Nov 2021)
  7. NASA NTRS: Holden et al. 2026, communication delay study methods (5–12 s) (2026)
  8. Gaier, NASA/TM-2005-213610: Effects of lunar dust on EVA systems during Apollo (2005)
  9. NASA: Environmental Control and Life Support Systems reference (Apr 2025)
  10. NASA Moon Base – Phases (2026)
  11. European Spaceflight: ASI awards new lunar habitat contract to Thales Alenia Space (MPH: 3 m × 6 m, ~15 t, 2 crew, 7–30 days a year) (Jul 2025)
  12. NASA OIG: Spacesuit development delays could impact Artemis timeline and ISS operations (demonstrations could slip to 2031) (Apr 2026)